The following activities have been carried out over the division.
Removal of redundant overhead lines:
Redundant overhead lines have been removed duly laying UG cables at North
Lallaguda and Medchal Sections.
Before removal of OH lines
Fig. Before Fig: After
After removing OH lines
Checking and ensuring firmness of electrical joints.
A drive has been conducted to check all the joints and terminations in MDBs, and
other sub distribution boards for any loose joints and ensured the firmness.
Checking of joints and terminations