Page 25 - GM booklet 2019 test
P. 25

ENGINEERING



            1.    Progress  of  Through  Weld  Renewal  work with  Mobile  Flash  Butt  Welding
            Plant

                                         2019-20
                   Item                      Progress up to                    REMARKS
                               Target
                                                Nov 2019
                                                                 Work  in  progress  on  SC-DHNE
                   TWR         08 Km            4.490 Km
                                                                 section















            2. Progress of Deep Screening with BCM machine

                                               2019-20
                     Item                         Progress up to                    Remarks
                                     Target
                                                     Nov 2019
               Deep Screening         50Km          27.825 Km         Work  in  progress  on  SC-DHNE
                  with BCM                                            section

















            3. Progress of Through Rail Renewal (P) Work

                                      2018-19
               Item                      Progress up to                          Remarks
                           Target
                                            Nov 2019
                                                              Work  in  progress  on  SC-DHNE  section.
             TRR (P)      14.53 Km          7.530 Km          Rails available for 1.0 Tkm.
                                                              Rails required for 6.0 Tkm.