1. Progress of Through Weld Renewal work with Mobile Flash Butt Welding
Plant
2019-20
Item Progress up to REMARKS
Target
Nov 2019
Work in progress on SC-DHNE
TWR 08 Km 4.490 Km
section
2. Progress of Deep Screening with BCM machine
2019-20
Item Progress up to Remarks
Target
Nov 2019
Deep Screening 50Km 27.825 Km Work in progress on SC-DHNE
with BCM section
3. Progress of Through Rail Renewal (P) Work
2018-19
Item Progress up to Remarks
Target
Nov 2019
Work in progress on SC-DHNE section.
TRR (P) 14.53 Km 7.530 Km Rails available for 1.0 Tkm.
Rails required for 6.0 Tkm.