6.  Canal  Crossing works: The  work of  Canal Crossing  at  Km  387/600-700  on  SC-MUE
            section has been taken up and completed duly inserting the Girder on 08.06.2019, RCC box
            provided under the track with cast insitu method and girder removed on 03.11.2019.

















            7. Improvement to TGI

            TRC run was carried out on SC-MUE section in Feb‟19 and following is the trend over a
            period of time, latest being the best.


                                    Section     Month of TRC run        TGI Achieved
                                                       Nov‟14                 98

                                                       Aug‟14                 93
                                                       Jan‟15                 86
                                   SC-MUE
                                                       July‟15                95
                                                      April‟16                93
                                                       Feb’19                104

            8. Non-Interlocking works

                 AKE station

            The work of non interlocking at AKE station has been taken up and completed in connection
            with construction of New BG line between AKE – MEDAK stations (17.20 Km) in May-2019.

                 MOB station

            Yard arrangements commissioned in connection with new line works between Manoharabad
            – Kothapalli (148.90 Kms) on 01.06.2019