6. Canal Crossing works: The work of Canal Crossing at Km 387/600-700 on SC-MUE
section has been taken up and completed duly inserting the Girder on 08.06.2019, RCC box
provided under the track with cast insitu method and girder removed on 03.11.2019.
7. Improvement to TGI
TRC run was carried out on SC-MUE section in Feb‟19 and following is the trend over a
period of time, latest being the best.
Section Month of TRC run TGI Achieved
Nov‟14 98
Aug‟14 93
Jan‟15 86
SC-MUE
July‟15 95
April‟16 93
Feb’19 104
8. Non-Interlocking works
AKE station
The work of non interlocking at AKE station has been taken up and completed in connection
with construction of New BG line between AKE – MEDAK stations (17.20 Km) in May-2019.
MOB station
Yard arrangements commissioned in connection with new line works between Manoharabad
– Kothapalli (148.90 Kms) on 01.06.2019