4. Through formation Treatment with Moorum Blanketing: The work of Through
Formation Treatment has been started on SC-DHNE section and a progress of 1.020 Km
has been achieved.
5.Elimination of Manned Level Crossings
Target 2019-20
Type of
Elimination PHOD Board Cumulative Progress
Direct Closure -
1 1
Diversion 1
(LC No: 148)
6
(LC No: 11, 21,56, 82, 101 on SC-
RUB 27 12
DHNE section, LC No: 239 on SC-
MUE section)
1
ROB 1 1
(LC No: 4 on GWD-RC section)
29 14 * 8
* Board‟s Target raised from 09 to 14 vide Hqrs letter no: W/287/LC/Tgt/Vol III Dt
29.10.2019.