5.  In  connection  with  New  Line  between  Manoharabad  –  Kothapalli,  remodeling
                       of yard carried out at MOB. The following assets have been installed:

                        Existing panel interlocking replaced with Electronic interlocking of M/s Medha
                          Servo Drives Pvt. Ltd.
                        Existing  IPS  of  Amara  raja  make  (old  RDSO  spn  165/2000)  replaced  with
                          Statcon make (Latest RDSO Spn 165/2012).






























               6.  Emergency  standby  Sliding  Boom  Barriers  provided  at  03  interlocked  LC
                   gates.  In  overall,  59  interlocked  LC  gates  have  been  provided  with  sliding
                   booms out of total 83 interlocked LC gates in the division.