6.  Passenger Train No. 57448 in DN direction and Train No. 57602 in UP direction are
                   run with Electric Loco on 20/21.09.2019 in KCG – MED section and no safety related
                   issues were found and no infringements.















               7.  New SCADA system [Latest spec. 0130, Rev.2] commissioned in TPC/HYB.
                   New RTU commissioned at SC/SSP, KCG/SSP, SFX/SP, BMO/SSP & MED/SSP by
                   M/s. Synergy Systems and Solutions Pvt. Ltd, Faridabad.


                   “Special Drives” attended by Division  :

                All    Special  drives  has  been  conducted  to  improve  reliability  by  Stagger  Checking  &
                Jumper checking/Adjustment  etc.,  done  in  sections SC  –  FM,  SC  –  MJF  -     MLY‟C  &
                MJF – BMO as per SED as per HQ instructions.


                   Special  Works carried out in HYB division:

               1.  Staff were deputed for RVNL works at BMO, FM for Loading and Un-loading of masts
                   and Erection of masts and DA‟s at FM - BDVL section.

               2.  Model OHE was commissioned at KCG Depot.