Page 91 - GM booklet 2019 test
P. 91

OPERATING


            Commissioning of doubling and yard arrangements for new lines

               1.  Bolarum  –  Medchal  (13.87  kms):  Doubling  and  electrification  commissioned  on
                   02.04.2019.

               2.  Akkanapet:  Additional  loop  line  commissioned  in  connection  with  new  line  works
                   between Akkanapet – Medak (17.20 kms) on 18.05.2019.


               3.  Manoharabad: Yard arrangements commissioned in connection with new line works
                   between Manoharabad – Kothapalli (148.90 Kms) on 01.06.2019.

            Coaching

                i.  Punctuality:
                   The punctuality performance of Express trains is 92.2% as against 91.7 % of last year
                   (April-Nov) which is 0.5% more.

               ii.  Special trains:
                   243  Special  Trains  were  run  from  KCG/NZB/KRNT  and  Rs.  13.7  Crs  earnings,  as
                   against 156 Special Trains and Rs. 10.05 Crs earnings of last year (April-Nov) which
                   is 36 % more.

               iii.  Augmentation of coaches:
                   a.  465  extra  coaches  are  augmented  in  various  trains  to  clear  extra  rush  of
                       passengers, which earned an amount of Rs. 1.3 Crs (April to Nov).
                   b.  12 car MMTS was introduced by augmenting of additional 3 cars from 01-05-2019.

               iv.  Traffic blocks
                   Traffic Blocks of 6507 hours are granted as against 6494 hours of last year (April-
                   Nov) for the works of Machine / Maintenance / RUB etc.

            Freight

            i.     Loading:

                 Loading  of  the  division  is  0.658  MT  as  against  0.728  MT  of  last  year  (April-Nov),
                   which is 9.6% less and 353.5 rakes as against 353 rakes loaded in last year.

                   a)  Container loading is 0.069 MT as against 0.052 MT of last year (April-Nov), which
                       is  32.7  %  more.  128  rakes  loaded  as  against  111  rakes  in  the  last  year  (April-
                       Nov), which is 15.3% more.
                   b)  Food grains‟ loading is 0.424 MT as against 0.453 MT of last year (April-Nov).141
                       FCI rakes loaded as against 137 FCI rakes in the last year (April-Nov).
                   c)  Other  revenue  loading  is  0.100  MT  as  against  0.176  MTof  last  year  which  is
                       43.2% less.