Page 86 - GM booklet 2019 test
P. 86

EMU CAR SHED , MOULA-ALI


              1.Introduction of 3- Phase EMU Rakes:

              New 3- Phase 12 Car rakes were inducted into service for passenger traffic w.e.f 01.05.2019.
              The existing 09- Car Rakes were augmented to 12 Car rakes and inducted into service w.e.f
              05.05.2019, thereby all the 10 Rakes of MMTS trains  in the existing routes SC-LPI-HYB-FM
              are augmented from 09 car to 12 Car and kept into service.







                                              12- Car 3- Phase & EMU (MMTS) Rakes

              2.Trouble shooting Directory (TSD) for 3-Phase EMU:


              Trouble  shooting  Directory  for  3-Phase  EMU  was  Unveiled  by  ADRM/O  and  ADRM/I  in
              presence of all BOs at DRMs Conference Hall of Hyderabad Division on 18.06.2019. This will
              facilitate LPs for Quick Trouble shooting of 3- Phase EMUs on line.















              3. Audio & Visual system to warn staff working in Pit lines

              All the 03 Pit lines of Inspection shed are provided with Hooter (Electronic Buzzer) & Bulb
              indication arrangement for alerting the maintenance staff working in the pit lines during
              Movement & Dispatch of Schedule Rakes.















                                   Bulb indication arrangement          Electronic Buzzer (Hooter)