Page 2 - A H - Engineering
P. 2

2. Progress of Deep Screening with BCM machine

                                                                            2020-21
                                 Item
                                                            Target         Progress up to Feb-2021
                Deep Screening with BCM                     70 Km                     76 Km
















                                       Deep screening work with BCM in the section.

            3. Progress of Through Rail Renewal (P) and Through Sleeper Renewal Works.

                                             2020-21
                      Item                       Progress up to                  Remarks
                                   Target
                                                    Feb 2021
                                                                      1.04  Tkm  Rails  (20  RP)
                     TRR (P)       07Km              5.93 Km          received  and  unloaded  on
                                                                      23.02.2021.
                     TSR (P)       05  Km             05 Km           Target achieved.


            4. Reduction in Asset Failures

                 Rail / Weld failures -   Division has achieved a reduction of 41 % over last year, In
                   the year 2020-21 Rail / Weld failures are10 Nos (Up to Feb‟21) compared to 17 Nos

                   in the year 2019-20 (Up to Feb‟20).


            5. Relaxation of Permanent Speed Restrictions.

                 Target 2020-21 = 02 Nos
                 Completed = 02 Nos


                                 Existing PSR
                                                                                        Remarks
            Sl
           No      Km       Section         SR            Reasons
                                                                          Relaxed to 100 Kmph in Jan‟2021
                 218/0-    IKI-MOA-                   Consolidation of  (Caution order of 04 Kms length
           01                            75 Kmph
                  222/0      ALPR                           Track         has been made as caution order of
                                                                          01 Km length)
                 491/0-                                 4 D curve in      Relaxed to 75 Kmph in Feb‟2021
           02              UPW-SCP       60 Kmph
                  492/0                                 Ghat section

                                                            21
   1   2   3   4   5   6   7