6.  Through  formation  Treatment  with  Moorum  Blanketing:  The  work  of  Through
            Formation  Treatment  is in  progress  in  SC-MUE  section  and  a  progress  of  7.910  Km has
            been achieved till end of Feb‟21.


















                    Through Formation Treatment work on SC-MUE section between DAB-KEK stations

            7.  Canal  Crossing  Works:  Canal Crossing  work between  KEK-DAB  stations  in  SC-MUE
            section is completed duly inserting the girder on 16.05.2020 and further the girder has been
            removed  after completing the box casting work under the track on 29.07.2020.
















                                  RUB Casting work at Canal crossing between KEK-DAB

            8. Increase in Sectional Speeds and New lines.

               a.  Sectional Speeds

                 FM-DHNE Section – CRS sanction received for Raising of sectional speed from 100
                   to 110 Kmph on 02.12.2020 and same has been implemented.

                 SHNR  –GLY  (New  Double  Line)  –  Double  line  commissioned  in  the  month  of
                   Sept‟20 with MPS 75 Kmph and PCE approval received for increasing speed from 75
                   to 100 Kmph on 03.02.2021, same will be implemented by 31.03.2021.

               b.  New Lines

                 Jaklair – Makthal - new line (11 Km) – Commissioned in the month of June‟20, to be
                   taken over by open line from construction.

                 Manoharabad  –  Gajwel  -  new  line  (33  Km)  –  Commissioned  in  the  month  of
                   June‟20, to be taken over by open line from construction.

                 Shadnagar – Gollapalli – Double line (DN Line) (30 Km) – Commissioned in the
                   month of Sept‟20, taken over by open line.