6. Through formation Treatment with Moorum Blanketing: The work of Through
Formation Treatment is in progress in SC-MUE section and a progress of 7.910 Km has
been achieved till end of Feb‟21.
Through Formation Treatment work on SC-MUE section between DAB-KEK stations
7. Canal Crossing Works: Canal Crossing work between KEK-DAB stations in SC-MUE
section is completed duly inserting the girder on 16.05.2020 and further the girder has been
removed after completing the box casting work under the track on 29.07.2020.
RUB Casting work at Canal crossing between KEK-DAB
8. Increase in Sectional Speeds and New lines.
a. Sectional Speeds
FM-DHNE Section – CRS sanction received for Raising of sectional speed from 100
to 110 Kmph on 02.12.2020 and same has been implemented.
SHNR –GLY (New Double Line) – Double line commissioned in the month of
Sept‟20 with MPS 75 Kmph and PCE approval received for increasing speed from 75
to 100 Kmph on 03.02.2021, same will be implemented by 31.03.2021.
b. New Lines
Jaklair – Makthal - new line (11 Km) – Commissioned in the month of June‟20, to be
taken over by open line from construction.
Manoharabad – Gajwel - new line (33 Km) – Commissioned in the month of
June‟20, to be taken over by open line from construction.
Shadnagar – Gollapalli – Double line (DN Line) (30 Km) – Commissioned in the
month of Sept‟20, taken over by open line.