MOCKDRILLS
MOCK DRILL AT FGD RIHAND PROJECT
Emergency for which mock-drill is conduct: Trip Hazard
Type of mock-drill: Practice Drill
Overall response time: 15 mnts
Sr. No. Good points of mock drill Observed shortfall in mock drill
Workers (M/S KUNAL) called to site supervisor & First Aider was not worn PPE's at location.
01
EHS person called to Ambulance.
Responsible person picked up the phone call on First Aider did not give first aid treatment at
02 time and reached the location. Worker M/SKUNAL the location of the victim.
guided the Ambulance to the location.
Corrective actions initiated related to observed
Sr. No. Responsibility Target
shortfall in mock drill, Area of improvement
Notified to First aider always first aid treatment to Jaiprakash Gupta & Immediate after
01
be done at location. Notified to first aider Respective contractor mock drill
regarding mandatory PPE and always wear EHS
mandatory PPE at site