Page 140 - Microsoft Word - 20120528 Unesco study
P. 140

Step 2: Leveling and pre-compaction
                  The second step is leveling and compaction of the trace. This have to be done prior to the
                  further steps for a fast processing of the further layers. The extended calculations are given in
                  table 3.16:


                  2 PRECOMPACTION OF THE SOIL
                  Materials (DESCRIPTION):            AMOUNT      UNIT     COSTO  COST IN MEXICAN PESOS
                  Water pipe (not potable)               0,03000  m3                 $ 50,00                                   $ 1,50
                  COST IN MEXICAN PESOS FOR Materials                                                                $ 1,50

                  Labor (description):                 AMOUNT     UNIT    SALARIO  COST IN MEXICAN PESOS
                  Crew No. 1 (1.00 Assistant)                     wage
                    Assistant                           1,00000  wage             $ 294,05                              $ 294,05
                    Specialized foreman (cape)          0,20000  wage             $ 949,47                              $ 189,89
                    Minor tools                         0,03000  (%)labor           $ 483,94                                $ 14,52
                    Factor of safety equipment          0,05000  (%)labor           $ 483,94                                $ 24,20
                                                                            addition                              $ 522,66
                  EFFICIENCY                           400,00000
                  COST IN MEXICAN PESOS for labor:                                                                   $ 1,31

                  Equipment (DESCRIPTION):             AMOUNT     UNIT     RENT   COST IN MEXICAN PESOS
                  Soil Compactor with drum vibratory rammers
                  CP563C Caterpillar 145-hp and 11,700 tons of   0,01000  hora           $ 442,42                                   $ 4,42
                  operating weight with 2.13 m wide drum
                  COST IN MEXICAN PESOS FOR EQUIPMENT                                                                $ 4,42


                  TOTAL COSTS
                    Direct cost                                                                                     $ 7,23
                    Indirect                                                 6,47%                                  $ 0,47
                    Field indirect                                           4,00%                                  $ 0,29
                    Subtotal                                                                                        $ 7,98
                    Funding                                                  0,25%                                  $ 0,02
                    Subtotal                                                                                        $ 8,00

                    Utility                                                 10,53%                                  $ 0,84
                    Additional Charges                                       0,50%                                  $ 0,04
                                                       U N I T A R Y    C O S T [M2]                                   $ 8,89
                         Table 3: Unitary costs step2






















                                                                                                     94