Page 142 - Microsoft Word - 20120528 Unesco study
P. 142

Step 4: Applying of the Sub-base

                   4 APPLYING OF THE SUB-BASE
                  Subgrade material                   AMOUNT      UNIT     COSTO  COST IN MEXICAN PESOS
                  Subbase material                      1,00000   m3              $ 157,00                              $ 157,00
                  Water pipe (not potable)              0,10000   m3                $ 50,00                                   $ 5,00
                  Crew No 27 (1.00 Oficial + 7 laborer)  0,00444  wage        $ 2.948,05                                $ 13,09
                  Grader 14-H, de 215 hp, motor CAT 3306  0,10000  hour           $ 788,87                                $ 78,89
                  Soil Compactor with drum vibratory rammers CP563C
                  Caterpillar 145-hp and 11,700 tons of operating   0,10000  hour           $ 442,42                                $ 44,24
                  weight with 2.13 m wide drum
                                                                            addition                              $ 298,22
                  AMOUNT                                 1,00000
                  COSTS IN MEXICAN PESOS  FOR CONSTRUCTION                                                      $ 298,22

                  Survey:                             AMOUNT      UNIT     COSTO  COST IN MEXICAN PESOS
                  Topography basic with equipment.                m2
                    Lime                                0,00500  bulto              $ 29,00                                   $ 0,14
                    Bar / stakes                        0,01500   pza.                $ 5,00                                   $ 0,08
                    electric transit Includes topographer and rodman  0,01000  hora           $ 340,89                                   $ 3,41
                                                                            addition                                   $ 3,64
                  AMOUNT                                 4,00000
                  COST IN MEXICAN PESOS for Survey                                                                $ 14,56

                  TOTAL COSTS
                    Direct cost                                                                                $ 312,78
                    Indirect                                                 6,47%                                $ 20,24
                    Field indirect                                           4,00%                                $ 12,51
                    Subtotal                                                                                   $ 345,53
                    Funding                                                  0,25%                                  $ 0,86
                    Subtotal                                                                                   $ 346,39
                    Utility                                                 10,53%                                $ 36,47
                    Additional Charges                                       0,50%                                  $ 1,73
                                                       U N I T A R Y    C O S T [M3]                              $ 384,60
                         Table 6: Unitary costs step4

                  The costs per construction are summarized in the following table.

                                                  Soil type   1: Organic   clays  Soil type   2:       Clay  Soil type   3:       Sandy clay  Soil type   4:          Sand





                  Roadtype 1: Highways                           $ 96,15                   $ 96,15                 $ 115,38                 $ 115,38
                  Roadtype 2: Primary roads                      $ 96,15                   $ 96,15                 $ 115,38                 $ 115,38
                  Roadtype 3: Secondary roads                    $ 96,15                   $ 96,15                 $ 115,38                 $ 115,38
                  Roadtype 4: Rural roads                        $ 96,15                   $ 96,15                 $ 115,38                 $ 115,38
                  Roadtype 5: Access roads                       $ 96,15                   $ 96,15                 $ 115,38                 $ 115,38

                                                                                  2
                         Table 7: Summarized construction costs step 4 in Mexican Pesos per m


                                                                                                     96