Appendix 6:  Cost calculations RoadCem

                      constructions






                  Step 1: Scarifying, excavation and preparation
                  Depending of the situation the location have to be prepared. For the RoadCem construction is
                  assumed that the soil or existing pavement needs a pretreatment for a depth of the thickness
                  of the RoadCem-cement layer.

                                                                             3
                  In table 3.29 is a calculation made for the preparation costs of 1m .

                  Labor (description):                 AMOUNT     UNIT    SALARY  COST IN MEXICAN PESOS
                  Crew No. 1 (1.00 Assistant)                     wage
                    Assistant                           1,00000  wage             $ 294,05                              $ 294,05
                    Specialized foreman (cape)          0,20000  wage             $ 949,47                              $ 189,89
                    Minor tools                         0,03000  (%)labor           $ 483,94                                $ 14,52
                    Factor of safety equipment          0,05000  (%)labor           $ 483,94                                $ 24,20
                                                                            addition                              $ 522,66
                  EFFICIENCY                           160,00000
                                           3
                  COST IN MEXICAN PESOS for labor  [m ]:                                                             $ 3,27

                  Equipment (DESCRIPTION):             AMOUNT     UNIT     RENT   COST IN MEXICAN PESOS
                  Grader 14-H, de 215 hp, motor CAT 3306  0,02500  hour           $ 788,87                                 $ 19,72
                  Compactor CB 634C, de 145 hp, 11.7 ton, wide drum
                  2.13 m with crowbar roller (sheeps foot roller or   0,02500  hour           $ 454,27                                 $ 11,36
                  vibratory foot roller)
                                                3
                  COST IN MEXICAN PESOS FOR EQUIPMENT [m ]                                                        $ 31,08

                  TOTAL COSTS
                    Direct cost                                                                                   $ 34,35
                    Indirect                                                 6,47%                                  $ 2,22
                    Field indirect                                           4,00%                                  $ 1,37
                    Subtotal                                                                                      $ 37,94
                    Funding                                                  0,25%                                  $ 0,09
                    Subtotal                                                                                      $ 38,03
                    Utility                                                 10,53%                                  $ 4,00
                    Additional Charges
                                                                             0,50%                                  $ 0,19
                                                                      3
                                                     U N I T A R Y    C O S T [m ]                                $ 42,22
                         Table 11:     Unitary costs step 1



                                                                                                   2
                  Depending of the thickness of the RoadCem cement layer construction will the price per m
                  calculated. In table 3.30 are the costs for the preparation per construction summarized: