Page 146 - Microsoft Word - 20120528 Unesco study
P. 146
Appendix 6: Cost calculations RoadCem
constructions
Step 1: Scarifying, excavation and preparation
Depending of the situation the location have to be prepared. For the RoadCem construction is
assumed that the soil or existing pavement needs a pretreatment for a depth of the thickness
of the RoadCem-cement layer.
3
In table 3.29 is a calculation made for the preparation costs of 1m .
Labor (description): AMOUNT UNIT SALARY COST IN MEXICAN PESOS
Crew No. 1 (1.00 Assistant) wage
Assistant 1,00000 wage $ 294,05 $ 294,05
Specialized foreman (cape) 0,20000 wage $ 949,47 $ 189,89
Minor tools 0,03000 (%)labor $ 483,94 $ 14,52
Factor of safety equipment 0,05000 (%)labor $ 483,94 $ 24,20
addition $ 522,66
EFFICIENCY 160,00000
3
COST IN MEXICAN PESOS for labor [m ]: $ 3,27
Equipment (DESCRIPTION): AMOUNT UNIT RENT COST IN MEXICAN PESOS
Grader 14-H, de 215 hp, motor CAT 3306 0,02500 hour $ 788,87 $ 19,72
Compactor CB 634C, de 145 hp, 11.7 ton, wide drum
2.13 m with crowbar roller (sheeps foot roller or 0,02500 hour $ 454,27 $ 11,36
vibratory foot roller)
3
COST IN MEXICAN PESOS FOR EQUIPMENT [m ] $ 31,08
TOTAL COSTS
Direct cost $ 34,35
Indirect 6,47% $ 2,22
Field indirect 4,00% $ 1,37
Subtotal $ 37,94
Funding 0,25% $ 0,09
Subtotal $ 38,03
Utility 10,53% $ 4,00
Additional Charges
0,50% $ 0,19
3
U N I T A R Y C O S T [m ] $ 42,22
Table 11: Unitary costs step 1
2
Depending of the thickness of the RoadCem cement layer construction will the price per m
calculated. In table 3.30 are the costs for the preparation per construction summarized:
100