Page 143 - Microsoft Word - 20120528 Unesco study
P. 143
Step 5: Applying of the Base course
5 APPLYING OF THE BASE-COURSE
Subgrade material AMOUNT UNIT COSTO COST IN MEXICAN PESOS
basecourse material 1,00000 m3 $ 180,00 $ 180,00
Water pipe (not potable) 0,10000 m3 $ 50,00 $ 5,00
Crew No 27 (1.00 Oficial + 7 laborer) 0,00444 wage $ 2.948,05 $ 13,09
Grader 14-H, de 215 hp, motor CAT 3306 0,10000 hour $ 788,87 $ 78,89
Soil Compactor with drum vibratory rammers CP563C
Caterpillar 145-hp and 11,700 tons of operating 0,10000 hour $ 442,42 $ 44,24
weight with 2.13 m wide drum
addition $ 321,22
AMOUNT 1,00000
COSTS IN MEXICAN PESOS FOR CONSTRUCTION $ 321,22
Survey: AMOUNT UNIT COSTO COST IN MEXICAN PESOS
Topography basic with equipment. m2
Lime 0,00500 bulto $ 29,00 $ 0,14
Bar / stakes 0,01500 pza. $ 5,00 $ 0,08
electric transit Includes topographer and rodman 0,01000 hora $ 340,89 $ 3,41
addition $ 3,64
AMOUNT 4,00000
COST IN MEXICAN PESOS for Survey $ 14,56
TOTAL COSTS
Direct cost $ 335,78
Indirect 6,47% $ 21,72
Field indirect 4,00% $ 13,43
Subtotal $ 370,93
Funding
0,25% $ 0,93
Subtotal $ 371,86
Utility 10,53% $ 39,16
Additional Charges 0,50% $ 1,86
U N I T A R Y C O S T [M3] $ 412,88
Table 8: Unitary costs step 5
The costs per construction are summarized in table 3.22.
Soil type 1: Organic clays Soil type 2: Clay Soil type 3: Sandy clay Soil type 4: Sand
Roadtype 1: Highways $ 103,22 $ 103,22 $ 103,22 $ 103,22
Roadtype 2: Primary roads $ 103,22 $ 103,22 $ 103,22 $ 103,22
Roadtype 3: Secondary roads $ 103,22 $ 103,22 $ 103,22 $ 103,22
Roadtype 4: Rural roads $ 103,22 $ 103,22 $ 103,22 $ 103,22
Roadtype 5: Access roads $ 103,22 $ 103,22 $ 103,22 $ 103,22
2
Table 9: Summarized construction costs step 5 in Mexican Pesos per m
97