2.3 Provision of Products or Services
The Company’s business policy is to maximize customers’ benefits by rendering top quality services
to sufficiently serve customers’ needs while taking into consideration the efficient use of natural resources along
with the preservation of watersheds and water resources as well as the lifestyle of the surrounding communities.
Business activities conducted at Amata City Chonburi Industrial Estate
2.3.1 Water Resources
3
• Si Yad Dam 5 mil m / year
3
• Amata Reservoir 24.7 mil m / year
3
• Other Reservoirs 17.5 mil m / year
3
• Water Reclamation 6.2 mil m / year
2.3.2 Production
3
• Treated Water Plant No. 1 with production capacity of 32,400 m / day
• Treated Water Plant No. 2 with production capacity of 21,000 m / day
3
3
• Treated Water Plant No.3 with production capacity of 10,000 m / day
3
• Water Reclamation Plant No.1 production capacity of 10,000 m / day
3
• Water Reclamation Plant No.2 production capacity of 7,000 m / day
• Water Reclamation Plant No.3 production capacity of 2,000 m / day
3
3
• Wastewater Treatment Plant No. 1 with production capacity of 24,000 m / day
3
• Wastewater Treatment Plant No. 2 with production capacity of 12,000 m / day
3
• Wastewater Treatment Plant No. 3 with production capacity of 4,500 m / day
3
• Wastewater Treatment Plant No. 4 with production capacity of 10,000 m / day
Business activities conducted at Amata City Rayong Industrial Estate
2.3.3 Water Resources
3
• Amata City Rayong Reservoir 3.5 mil m / year
3
• Natural Resources 8.3 mil m / year
3
• Other Reservoirs 16 mil m / year
3
• Water Reclamation 5.5 mil m / year
2.3.4 Production
3
• Treated Water Plant No. 1/1 with production capacity of 18,000 m / day
3
• Treated Water Plant No. 1/2 with production capacity of 15,000 m / day
3
• Treated Water Plant No. 2 with production capacity of 10,500 m / day
• Water Reclamation Plant No.1 production capacity of 9,360 m / day
3
3
• Water Reclamation Plant No.2 production capacity of 7,000 m / day
3
• Wastewater Treatment Plant No. 1 with production capacity of 16,500 m / day
• Wastewater Treatment Plant No. 2 with production capacity of 9,600 m / day
3
• Wastewater Treatment Plant No. 4 with production capacity of 10,000 m / day
3
Amata Corporation Public Company Limited 45