Page 5 - COMPREHENSIVE_SITE_ASSESSMENT_REPORT_IMAGES_FOR_VOLUME_03
P. 5
HEAD OFFICE |VAT REGISTRATION NUMBER |4960317727 FLEET & EQUIPMENT
PHYSICAL ADDRESS:Ground Floor – Building 2 |NHBRC REGISTRATION NUMBER |4000013824 IN-HOUSE EARTHMOVING FLEET UNITS) INSURANCE
|CIDB GRADING DESIGNATION | GNSS RTK SURVEY EQUIPMENT PUBLIC LIABILITY COVER| R5 MILLION
Gleneagles Park 10Flanders Drive Mount Edgecombe |CSD SUPPLIER NUMBER | SCAFFOLDING & FORMWORK SYSTEMS PROFESSIONAL INDEMNITY| R2MILLION
POSTAL ADDRESS: P.O. Box 582 Westville 3630 TAX CLEARANCE CERTIFICATE |SARS COMPLIANT HUMAN RESOURCES ALL RISK COVER | R10 MILLION
|B-BBEE LEVEL |LEVEL 1 BARGAINING COUNCIL REGISTRATION|BCAWU COMPLIANT BANK DETAILS
TEL: +27 73 557 1040 Fax:
CSD SUPPLIER NUMBER |REGISTERED PERMANENT CREW |TRAINED ARTISANS PERSONNEL ACCOUNT TYPE | BUSINESS CHEQUE ACCOUNT
EMAIL: admin@dsonindustries.co.za MASTER BUILDERS ASSOCIATION |MEMBER QUALIFIED SITE SAFETY OFFICERS --2 |FIRST NATIONAL BANK — ACC NO: 63104084883, |
WEBSITE: www.dsonindustries.co.za CIVIL ENGINEERING & CONSTRUCTION WORKS INHOUSE ENGINEERS AND DRAUGHTSMAN BRANCH WESTVILLE (250655), SWIFT: FIRNZAJJ |
FULL SAFETY COMPLIANCE (ISO 45001/OHS ACT) ACCOUNT TYPE | BUSINESS CHEQUE ACCOUNT
Description Amount (ZAR)
GRAND TOTAL (Including VAT) R798,387.50
◄ ►
Total Investment for Consideration: R798,387.50
(Seven Hundred and Ninety-Eight Thousand Three Hundred and Eighty-Seven Rand and Fifty Cents)
◄
7.3 COMMERCIAL TERMS ►
Term Condition
Validity Period Valid until 30 April 2026
Rate Basis Fixed for duration of works (no escalation)
Payment Terms As per your established protocols
Commencement Subject to approval and site handover
Roads: 15 working days I Wall: 10 working days
Completion
◄ ►
8. ADDITIONAL INFRASTRUCTURE FOR FUTURE CONSIDERATION
Volume 3 of this assessment series will provide detailed analysis of the following elements, which may benefit from
future attention:
Stormwater & Erosion Management
Slope Stability & Platform Systems
Comprehensive Drainage Integration
Infrastructure Monitoring & Maintenance Protocols
(Detailed findings, proposed interventions, and associated investment estimates will be presented in Volume 3)
9. RECOMMENDATIONS FOR CONSIDERATION
We respectfully submit the following suggestions for your consideration, recognizing that decisions regarding
infrastructure investment and implementation approach rest with your experienced management team.
9.1 POTENTIAL 2026 PRIORITIES
From our observations, the following may warrant consideration within your 2026 planning:
Priority Works Under This Proposal (R798,387.50 including VAT):