130 ERECTING CRIB WALLS
      • Headers and all joints in the stretchers: Butted and vertically aligned.
      • First row of stretchers: Position and retain with header units.
      • Header support blocks: As recommended by crib wall manufacturer.
      • Unit fill/ Backfill:
          - To top of each course of stretchers as work proceeds.
          - Compact in layers maximum 200 mm deep.

210 GABIONS
      • Manufacturer: Contractor's choice.
          - Product reference: Contractor's choice.
          - Sizes: site specific.
          - Mesh: site specific.
          - Diaphragm: site specific.
      • Fill to units:
          - Material: site specific.
          - Size/ grading: site specific.
      • Substrate: Concrete as section E10, site specific thickness.
          - Batter of wall face: Vertical.
      • Geotextile: site specific.
      • Other requirements: site specific.

230 BASTIONS
      • Manufacturer: Contractor's choice.
          - Product reference: Contractor's choice.
          - Sizes: site specific.
          - Mesh: site specific.
          - Insert panel: site specific.
          - Lining: Nonwoven geotextile.
      • Fill material to units generally: site specific.
      • Face fill material: site specific.
      • Substrate: Existing granular bed cut to required batter.
          - Batter of wall face: Front face vertically aligned.
      • Other requirements: site specific.

240 GEOTEXTILE
      • Manufacturer: Contractor's choice.
          - Product reference: Contractor's choice.
          - Permeability: site specific.
      • Recycled content: site specific.
      • Jointing:
          - End and side laps: Minimum 300 mm.
      • Timing: Do not lay more textile than will be covered in the same day.