Page 410 - Mines Facilities Plan
P. 410
provide its mechanical cooling. The Engineering Annex is only partially cooled
Hall has some distributed direct expansion cooling and some window cooling
units. Engineering Hall has rooftop direct expansion air handing units which
Steinhauer Field House does not have any mechanical cooling. Chauvenet
with rooftop direct expansion air handling units.
INNOVATION HUB The Innovation Hub neighborhood does not house any chilled water plants. The existing buildings either do not have any cooling or have stand-alone plants. Both the General Research Lab (GRL) and the General Research Lab Annex have stand-alone chillers that serve their respective buildings. WEST CAMPUS West Campus houses one (1) chiller plant, Chiller Plant 6 (CP6). CP6 is located within Brown Hall and has a current capacity of 1,300
The remaining buildings within Central Campus are Steinhauer Field House,
(Model # YMC2-S11892AB) 538 ton chillers installed in 2017. CP7 currently
CP7 is located within the Green Center. This plant was recently constructed
These mains have existing taps for a future connection to Stratton Hall and
provides chilled water to the Green Conference and Arts Center, Hill Hall,
CHILLED WATER: EXISTING SITE PLAN in 2018 and has a capacity of 1,614 tons. It houses three (3) new York and Coolbaugh Hall via 14” chilled water lines supply and return mains. Chauvenet Hall and terminate as capped 14” supply and return mains for other future connections. The current total connected equipment cooling capacity is 1,345 tons, not considering diversity. Chauvenet Hall, Engineering Hall, and the Engineering Annex. Curren