                    ■ The  following  shop  drawings  and  submittals   Additional Services and Exclusions
                    will be reviewed:
                    •  Concrete  wall  panels  (architectural     We can provide Additional Services at your request
                       features).                                 if the scope of the project or our services  changes
                    •  Miscellaneous metals (roof ladder, railings,   for a mutually agreed upon fixed fee or on an hourly
                       steps).                                    basis at our standard hourly rates. Examples of
                    •  Aluminum and glass.
                    •  Doors, frames, and hardware.               Additional Services would include:
                    •  Dock equipment.
                    •  Roofing.                                       ■ Making  Owner-requested  revisions  to
                    •  Structural components.                         previously approved drawings.
                    •  Mechanical, plumbing, and electrical           ■ Making “value engineering” changes to the
                       components.                                    drawings after receipt of bids.
                    ■ Answer contractor Requests for Information      ■ Preparing an artist’s rendering of the building.
                    (RFIs).  We have included a budget of fifty (50)     ■ Preparing book-format specifications.
                    hours for this service.                           ■ Making additional site visits or answering
                                                                      RFIs during construction beyond the scope
               Please note that it is our goal to maintain flexibility   listed above.
               in the performance of our services during this         ■ Reviewing submittals not listed above.
               phase  and  render  the  most  appropriate  level  of     ■ Preparing documentation for tenant fit-out or
               service.  We can modify our scope of services upon     other interior improvements.
               your request with an adjustment in compensation.       ■ Project closeout services including but not
                                                                      limited to record drawings and as-built
                                                                      documentation.
               Compensation                                           ■ Providing services after a substantial delay in
                                                                      the project schedule.
                 Basic Services
                 We propose to perform the Basic Services         The following are not included in our scope:
                 described above for a lump sum fixed fee in
                 accordance with the compensation schedule            ■ Geotechnical (soils) engineering.
                 included herein as Exhibit A – Design RFP Cost       ■ Civil engineering and landscape architecture.
                 Breakdown.  Hourly rates are included in Exhibit     ■ Mechanical,  plumbing,  and  electrical
                 B – Hourly Rate Schedule.                            engineering.
                                                                      ■ Fire suppression (sprinkler) final design.
                 Reimbursable Expenses                                ■ Construction cost estimating.
                 Reimbursable expenses (such as printing,
                 overnight delivery, air travel, mileage, meals,
                 overnight accommodations, etc.) are not included
                 in the above professional fees and will be invoiced
                 based upon actual costs expended times 1.10.




               BERNARDON  |  Response to Request for Proposal for Design Services                          Page 4
               Equus Development, L.P.   |  104 Guilford College Road, Greensboro, NC  |  July 30, 2021
   2   3   4   5   6   7   8   9   10   11   12