Page 8 - Bernardon-Equus Greensboro NC Warehouse RFP Response_Neat
P. 8
www.bernardon.com
Exhibit A - Design RFP Cost Breakdown
Services (Greensboro)
Schematic Design
Architectural $12,000
Structural $4,000
M/E/P/FP $3,000
Subtotal $19,000
Design Development
Architectural $20,000
Structural $5,500
M/E/P/FP $10,000
Subtotal $35,500
Construction Documents
Architectural $40,000
Structural $13,700
M/E/P/FP $13,000
Subtotal $66,700
Bidding & Award
Architectural $2,500
Structural $400
M/E/P/FP $1,000
Subtotal $3,900
Construction Administration
Architectural $93,000 Note 1
Structural $4,400
M/E/P/FP $4,200
Subtotal $101,600
Project Close-Out
Architectural (Scope not defined in RFP) Not included Note 2
Structural (Scope not defined in RFP) Not included Note 2
M/E/P/FP (Scope not defined in RFP) Not included Note 2
Subtotal Not included Note 2
Reimbursables Allowance $28,000 Note 3
Total $254,700
Unit Pricing
3-D Photorealistic Renderings - Aerial $3,000 each
3-D Photorealistic Renderings - Ground Level $3,000 each
Notes
1.) Twenty-three (23) on-site construction progress meetings included. We have included $3,000 per
meeting excluding expenses. Therefore, the total architectural fee value of Construction Administration
includes $69,000 associated with attending meetings at the project site. The remaining $24,000 is associated
with the other Construction Administration services outlined in the proposal.
2.) The specific scope of Project Close-Out was not defined in the RFP.
3.) We have included $800 per on-site construction progress meeting for travel expenses.
BERNARDON | Response to Request for Proposal for Design Services Page 5
Equus Development, L.P. | 104 Guilford College Road, Greensboro, NC | July 30, 2021