WORK PLAN
The project phases we have planned in our work activities include:
TASK SCHEMATIC PHASE
01 • Project kick-off meeting.
• Code research.
• Calculations.
• Investigation of mechanical, electrical, plumbing systems to accomplish the
desired result for the project.
• Preliminary document defining the VRF system and up to two (2) MEP/FP
system alternatives for Owner/Architect review and budgeting.
• Review of any special needs and identifying the most appropriate means of
achieving operational requirements.
• Prepare and submit S&M applications with that appropriate utility companies
• Preliminary coordination of utilities with Civil.
• Attendance at the allocated project/design meetings during this phase.
• Preparation of a narrative based schematic submission for owner review and
budgeting.
TASK DESIGN DEVELOPMENT
02 • Incorporate client, construction manager, and design assist team input from
schematic including MEP/FP system selections.
• Perform preliminary equipment selections and mechanical and electrical
space requirements based on budgetary input.
• Provide proposed domestic water room/fire pump room layouts, plumbing
riser locations, proposed utility connection locations.
• Provide proposed main electrical room layouts, corridor lighting and power
layouts, electrical distribution closet layouts.
• Provide proposed common area mechanical shaft locations, corridor
ductwork distribution, and rooftop mechanical equipment layout.
• Provide criteria for retail space MEP/FP systems.
• Provide preliminary parking garage lighting, power, ventilation, and drainage
design.
• Preparation of six (6) typical enlarged unit mechanical, electrical, and
plumbing plans for each the hotel and apartment/condo building
owner/architectural review.