             pressure overshoot
             Difference between maximum instantaneous pressure and set pressure.

             pressure purging (pulse purging)
             Total purging accomplished by successive pressurising and depressurising operations until an
             acceptable end-point is reached.

             pressure regulating installation (PRI)
             Assembly of equipment designed to regulate, or reduce, the pressure of gas.

             pressure regulating system
             Control system, the purpose of which is to hold pressure constant or to vary it in  a
             pre-determined manner.

             pressure safety system
             System which acts independently  and  which  ensures that outlet pressure does not exceed
             safety limits.

             pressure switch
             Switch that makes electrical contact when a certain set pressure been reached on its input.

             pressure transducer
             Device which converts gas pressure into an electrical signal proportional to that pressure.

             pressure regulating installation (PRI)/regulator inlet valve (PRIIV/RIV)
             Valve fitted upstream of, and adjacent to, a PRI/regulator to shut off the supply of gas.

             pressure regulating installation (PRI)/regulator outlet valve (PRIOV/ROV)
             Valve fitted downstream of, and adjacent to, a PRI/regulator to shut off the supply of gas.

             PRI station
             PRI, together with items which support it, such as the site, fencing, housing, etc.

             primary grade of release
             Release which can be expected to occur periodically or occasionally during normal operation.

             primary inlet
             Point where combustion air enters a SE-duct.

             primary meter
             Gas meter, the index  reading of which constitutes the  basis of charge for all gas supplied
             through that meter.

             Note:   This definition is a variation of the legal definition taken from GS(I&U)R.

             principal stresses
             At any point in pipework, the maximum and minimum compressive or tensile stresses at right
             angles to one another, calculated by combining the individual hoop, axial and shear stresses at
             that point.

             probability density
             Function which defines the relationship between the value of a parameter and the probability
             of occurrence of the value.

             product/product pipe
             Permanent pipeline, duct or cable being installed for operational use.

             programmable electronic system (PES)
             Electronic control system which embodies digital computing processes.