Page 189 - ADMINISTRATIVE MANUAL
P. 189

169


                                 x.   Percentages of planned and actual accomplishments, if applicable;
                                xi.   Value of outstanding works, if applicable
                                xii.   The statement shall be supported by the notices of award and/or notices
                                      to proceed issued by the owners; and
                               xiii.   The  statement  shall  be  supported  by  the  CPES  rating  sheets,  and/or
                                      certificates of completion and owner’s acceptance, if applicable

                            g.2 Similar or not similar in nature and complexity to the contract to be bid.

                       h)  Valid PCAB license and registration for the type and cost of the contract to be bid;
                       i)  The prospective bidder’s statement of:
                          i.1 Availability of the prospective bidder’s key personnel, such as project managers,
                              project  engineers,  materials  engineers  and  foreman,  that  may  be  used  for
                              construction contracts; and
                          i.2 Availability of equipment that he owns, has under lease, and/or has under purchase
                              agreements,  that  may  be  used  for  construction  contracts,  provided  that  the
                              ownership of equipment is not a requisite for eligibility; and
                      j) The prospective bidder’s audited financial statement, stamped “received” by the BIR or
                         its duly accredited and authorized institutions, for the immediately preceding calendar
                         year, showing, among others, the prospective bidder’s total and current assets and
                         liabilities.

                   2)  Class “B” Documents
                       a)  Valid joint venture agreement, in case of a joint venture; and
                       b)  Letter authorizing the BAC or its duly authorized representative/s to verify any or all of
                          the documents submitted for the eligibility check.

               The prospective bidder or its duly authorized shall certify under oath that each of the documents
               submitted in satisfaction of the eligibility requirements is as authentic and original copy, or a true
               and faithful reproduction or copy of the original, complete, and that all statement and information
               provided therein are true and correct.

               A prospective bidder may be allowed to submit his eligibility requirements electronically. Provided,
               however, that said prospective bidder shall submit the certification required to the BAC at least
               seven (7) calendar days before the deadline for the submission and opening of the eligibility
               envelopes. The entire process of eligibility check for the procurement of infrastructure projects
               shall not exceed fifteen (15) calendar days.


                   IV.    Pre-Bid Conference

               For contracts to be bid with an a approved budget of one million pesos (P1,000,000.00) or more,
               the  BAC  shall  convene  at  least  one  (1)  pre-bid  conference  to  clarify  and/or  explain  any
               requirements, terms, conditions and specifications stipulated in the bidding documents.

               For  contracts  to  be  bid  conference  less  than  one  million  pesos  (P1,000,000.00),  pre-bid
               conferences may be conducted at the discretion of the BAC. Subject to the approval of the BAC,
               a pre-bid conference upon written request of any prospective bidder.

               The pre-bid conferences shall be held at least twelve (12) calendar days before the deadline for
               the submission and receipt of bids. However, attendance of the bidders shall not be mandatory.
   184   185   186   187   188   189   190   191   192   193   194