               The pre-bid conference shall discuss, among other things, the technical and financial components
               of the contract to be bid. The minutes of the pre-bid conference shall be recorded and made
               available to all participants not later than three (3) calendar days after the pre-bid conference.

               Request for clarification(s) must be in writing and submitted to the BAC at least ten (10) calendar
               days before the deadline set for the submission and receipt of bids. The BAC shall respond to the
               said request by issuing a Supplemental/Bid Bulletin, at least seven (7) calendar days before the
               deadline for the submission and receipt of bids

               Any Supplemental Bulletin issued by the BAC shall also be posted on the website of the procuring
               entity concerned, if available, and on the G-EPS.


                   V.     Submission and Receipt of Bids

               Eligible  bidder  shall  submit  their  bids  through  their  authorized  officer  or  their  duly  authorized
               representative (i) in the prescribed Bid Form, including its annexes, as specified in the bidding
               documents,  (ii)  on  or  before  the  specified  deadline,  and  (iii)  in  two  (2)  separate  sealed  bid
               envelopes, the first containing the technical component of the bid, and second containing the
               financial component of the bid.

               Bid submitted after the deadline shall not be accepted by the BAC.

               The    first   envelope   (Technical   Proposal)   shall   contain   the   following   technical
               information/documents, at least:
                   1)  Bid security as to form, amount and validity period;
                   2)  Authority of signing official;
                   3)  Construction schedule and S-curve;
                   4)  Manpower schedule;
                   5)  Construction methods;
                   6)  Organization chart for the contract to be bid;
                   7)  List  of  contractor’s  personnel  (viz.,  project  managers,  project  engineers,  materials
                       engineers and foremen), to be assigned to the contract to be bid, with their complete
                       qualification and experience data;
                   8)  List of contractor’s equipment units, which are owned, leased, and/or under purchased
                       agreements, supported by certification of availability of equipment from the equipment
                       lessor/vendor for the duration of the project;
                   9)  Equipment utilization schedule;
                   10) Affidavit of site inspection
                   11) Commitment of the contractor’s bank to extend to it a credit line if awarded the contract to
                       be bid, or cash deposit certificate, in an amount not lower than that set by the agency in
                       the  Instruction  to  Bidders,  which  shall  be  at  least  equal  to  the  operating  cash  flow
                       requirement of the contract to be bid (i.e., the estimated average operating expense for
                       two (2) months of the contract to be bid, or ten percent (10%) of the approved budget for
                       the contract to be bid, whichever is less.)
                   12) Construction safety and health program of the contractor.
                   13) Certificate  from  the  bidder  under  oath  of  its  compliance  with  existing  labor  laws  and
                       standards;
                   14) A sworn affidavit of compliance with the Disclosure Provision of RA 9184 in relation to
                       other provisions of RA 3019; and