opening size until the 1 in 1 year event is
                                                                                                                                 the 1 in 100 flow rate - for example this
      Detailed Design  9.6.8  Sizing flow control openings       9.6.8.1  Approach 1 methodology                             4.  Make a note of the calculated opening              8.  Re-run the calculations for the 1 in 100          Detailed Design
                                                                                                                                                                                       attenuated to the 1 in 1 discharge rate and
                                                                                                                                 may be 350mm for a permeable
                                                                                                                                                                                       make a note of the resulting maximum
                                                                 An orifice opening will deliver variable
           The following methodologies for sizing flow
                                                                                                                                 pavement or up to 600mm for basins.
                                                                                                                                                                                       storage depth.
                                                                 outflow rates as the severity of rainfall
           controls are intended for use by those with
           knowledge of hydraulic calculations. Careful
                                                                 increases, producing and storing more runoff.
                                                                                                                                 size to achieve the 1 in 100 flow rate at
                                                                                                                                                                                       year event based on the changed
           consideration should always be given to the
                                                                 As the depth of stored water increases the
                                                                                                                                 this storage depth.
                                                                                                                                                                                       opening.  The maximum flow rate will now
           selection of equations and coefficients.
                                                                 gravitational pressure forces more flow
                                                                                                                             5.  Based on the same storage component
                                                                                                                                                                                       be below the allowable discharge rate
                                                                 through the opening - sometimes referred to
           Section 6.4.3.6 outlines two approaches for
                                                                                                                                 design and flow control opening, calculate
                                                                                                                                                                                       resulting in more storage than is
                                                                 as the ‘driving head’ of water stored.
           the control of flow, summarised as follows:
                                                                                                                                 – make a note of the maximum storage
                                                                                                                                                                                       opening may be placed above the 1 in 1
                                                                 The following steps outline the process of
           Approach 1 – Variable control
                                                                                                                                 depth and maximum flow rate. Note that
                                                                                                                                                                                       storage depth noted in step 7.  Add a
                                                                 calculating the opening size of an orifice flow                 how a 1 in 1 year rainfall event will behave          necessary.  To overcome this, a second
                                                                                                                                 the volume and therefore driving head will
           Non Statutory Technical Standard S2 allows            control to meet the requirements of NSTS S2:                    be significantly smaller for the 1 in 1 year          second opening so that it’s lower most
           for varying the outflow rate for the 1 in 1 year                                                                      rainfall event and therefore the flow rate            point (invert) is at or above the 1 in 1
                                                                                                                                                                                       storage depth and recalculate the storage
           and 1 in 100 year greenfield runoff rates for         1.  Establish the controlled outflow (or                        through the orifice will be significantly             behavior in a 1 in 100 event.  Adjust the
           the respective rainfall events.                           Greenfield runoff) rates for the 1 in 1 year                lower.                                                opening size and height above the 1 in 100
                                                                     and 1 in 100 year rainfall event.                       6.  If the calculated maximum flow is less                storage depth until the 1 in 100 flow rate is
           Approach 2 -  Qbar method                                                                                                                                                   achieved at the maximum storage depth
                                                                 2.  Define the first, lower orifice invert. A                   that the 1 in 1 year control rate then the
           Where the design requirements for volume                                                                              opening does not need changing.                       for the 1 in 100 event.Bo
                                                                     reasonable starting point is to set the
           control (S3) cannot be achieved then all                  invert at the base (or slightly below the               7.  If the calculated maximum flow for the 1 in
           runoff from the site for the 1 in 100 year event                                                                      1 event is larger than the 1 in 1 year control                      Design Notes:
                                                                     base) of storage.
           including CCA should be discharged at a                                                                               rate then reduce the opening size and                Both the 1 in 1 and 1 in 100 discharge
           maximum Qbar rate (or equivalent) for the             3.  Calculate the maximum storage depth for                     recalculate based on the 1 in 1 event being          rates can be achieved by any
                                                                     your SuDS component, based on its                           mindful that the 1 in 100 year scenario will
  99       development. A lower flow control threshold                                                                           have to be reconsidered.  Amend the                  combination of the following:                       100
           of 2 l/sec/ha is acceptable to enable                     catchment, for the 1 in 100 year event and                                                                          ■  Adjusting the depth of each defined
           reasonable drain down times.                                                                                                                                                   storage tier by adjusting the area and
                                                                                                                                                                                          therefore volume of each tier
           It is noted that the maximum Qbar rate is                                                                                                                                     ■
           only reached when the SuDS  component is                                                                                     required 1 in 100 flow rate                       Incorporating one or more additional
                                                                                                                                                                                          openings
           full and the design head reached.
                                                                                                                                                                                      Other options can be explored where
                                                                                                                                                                                      there is difficulty in matching outflow
                                                                         relationship between driving head and                          flow rates derived by area drained            rates for both the 1 in 1 year and 1 in 100
                                                                            flow through an orifice flow control                        and respective growth curve                   year flows:
                                                                                                                                                                                         ■  Try different types of openings such
                                                                   Head                                                                                                                   as rectangular and v-notch weirs.


                                                                                                                                                                                         ■  Store for a different return period – it
                                                                                                                                                                                          is not necessary to store for the 1 in
                                                                                                                                                                                          100 year return period in every sub-
                                                                                               required 1 in 1 flow rate                                                                  catchment. The final discharge from
                                                                                                                                                                                          the site must meet requirements of
                       Graph comparing required flow rates
                        and the variable flow rate through a                                                                                                                              NSTS.
                            simple orifice as head increases.                                                     Flow


           Newham Council SuDS D & E Guide                                                                        © 2020 McCloy Consulting & Robert Bray Associates  Newham Council SuDS D & E Guide                                                                        © 2020 McCloy Consulting & Robert Bray Associates