Page 75 - Newham SuDS DESIGN & EVALUATION GUIDE
P. 75

Detailed Design  9.3  Typical Detailed Design package   9.3.2  Drawing package                                    Detailed Design

 The Detailed Design package should be
      The SuDS drawing package should include
 proportionate to the scale of the
      the following:
 development and will generally encompass a
                        Topographical survey of the site
       Design
 design statement with accompanying
       information
 drawings. Supporting information including
                        Coordinated constraints map identifying all potential design constraints including
       drawings
 calculations, maintenance plan and risk
                        areas of flood risk (fluvial, pluvial and ground water), contaminated land,
 assessment will also be required.
                        archaeological significance, poor ground conditions, unexploded ordnance (UXO),
                        presence of invasive species, protected habitats, tree Protection Orders (TPO) and
                        root protection zones (RPZ). [note : list is not exhaustive]
 9.3.1  SuDS Design Statement   Existing utility services drawing. Details of existing site surface water drainage

                        infrastructure and ownership established
 The SuDS Design Statement should cover     ■  outline how requirements of NPPF, NSTS,
 SuDS provisions on quantity, quality, amenity   local SuDS policies, requirements for   Plan of site detailing flow routes including exceedance flow routes, subcatchment
 and biodiversity and how opportunities   multi-functional use of SuDS space and   boundaries, flow control locations, storage locations, contributing impermeable area,
 provided by the site have been maximised   local objectives for sustainability including   and phasing where appropriate;
 along with addressing the following:  climate resilience are dealt with  Drawing of site drainage catchment areas showing permeable and impermeable areas
                        within defined subcatcatchments.
   ■  confirm drainage design criteria agreed     ■  explain how SuDS will function passively
 with LPA. For example, rainfall return   in terms of treatment and management
 periods, discharge allowance, traffic   Design   Detailed site layout at an identified scale (1:200 or 1:500 or as appropriate or any other
 loading requirements etc    ■  outline details of any offsite works   drawings  scale agreed) including a North direction arrow.
 69     ■  summarise the findings of the FRA and   required, together with any necessary   Long sections and cross sections for the proposed drainage system, including   70
 consents.
 highlight any other significant site   surrounding site level and proposed finished floor levels (where appropriate)

 constraints            Construction Details – inlets, outlets, flow controls, storage, edge details, connection
                        details to receiving watercourse / sewers / public surface water sewers / highway
                        drains;

                        Planting arrangement and surface treatment / materials drawings where detailed not
                        included on other drawings.

                        Critical design levels should be identified on all relevant drawings.










      Facing:
      Rectory Gardens Rainpark, Hornsey.
      A small public park that collects polluted road
      runoff through silt forebays and underdrained
      infiltration basins that discharge clean water
      slowly to the River Moselle.


 London Borough of Newham SuDS D & E Guide                                                     © 2018 McCloy Consulting & Robert Bray Associates  London Borough of Newham SuDS D & E Guide                                                     © 2018 McCloy Consulting & Robert Bray Associates
   70   71   72   73   74   75   76   77   78   79   80