Page 111 - 2018_IRC
P. 111

BUILDING PLANNING



         R324.6 Roof access and pathways. Roof access, pathways    placed on the portion of a roof that is below an emer-
         and  setback  requirements  shall  be  provided  in  accordance  gency escape and rescue opening. A pathway not less
         with Sections R324.6.1 through R324.6.2.1. Access and min-  than 36 inches (914 mm) wide shall be provided to the
         imum spacing shall be required to provide emergency access  emergency escape and rescue opening.
         to the roof, to provide pathways to specific areas of the roof,  R324.7  Ground-mounted  photovoltaic  systems.  Ground-
         provide for smoke ventilation opportunity areas, and to pro-  mounted  photovoltaic  systems  shall  be  designed  and  in-
         vide emergency egress from the roof.                 stalled in accordance with Section R301.
           Exceptions:                                           R324.7.1  Fire  separation  distances.  Ground-mounted
              1. Detached, nonhabitable structures, including but not  photovoltaic systems shall be subject to the fire separation
                limited  to  detached  garages,  parking  shade  struc-  distance  requirements  determined  by  the  local  jurisdic-
                tures, carports, solar trellises and similar structures,  tion.
                shall not be required to provide roof access.
              2. Roof access, pathways and setbacks need not be pro-            SECTION R325
                vided  where  the  code  official  has  determined  that        MEZZANINES
                rooftop operations will not be employed.
                                                              R325.1  General.  Mezzanines  shall  comply  with  Sections
              3. These  requirements  shall  not  apply  to  roofs  with  R325  through  R325.5.  Habitable attics  shall  comply  with
                slopes  of  two  units  vertical  in  12  units  horizontal  Section R325.6.
                (17-percent slope) or less.
                                                              R325.2 Mezzanines. The clear height above and below mezza-
           R324.6.1  Pathways.  Not  fewer  than  two  pathways,  on  nine floor construction shall be not less than 7 feet (2134 mm).
           separate roof planes from lowest roof edge to ridge and
           not less than 36 inches (914 mm) wide, shall be provided  R325.3 Area limitation. The aggregate area of a mezzanine
           on  all  buildings.  Not  fewer  than  one  pathway  shall  be  or mezzanines shall be not greater than one-third of the floor
           provided on the street or driveway side of the roof. For  area  of  the  room  or  space  in  which  they  are  located.  The
           each roof plane with a photovoltaic array, a pathway not  enclosed portion of a room shall not be included in a determi-
           less  than  36  inches  wide  (914  mm)  shall  be  provided  nation of the floor area of the room in which the mezzanine is
           from the lowest roof edge to ridge on the same roof plane  located.
           as the photovoltaic array, on an adjacent roof plane, or  Exception:  The  aggregate  area  of  a  mezzanine  located
           straddling the same and adjacent roof planes. Pathways  within a dwelling unit equipped with a fire sprinkler sys-
           shall  be  over  areas  capable  of  supporting  fire  fighters  tem in accordance with Section P2904 shall not be greater
           accessing  the  roof.  Pathways  shall  be  located  in  areas  than one-half of the floor area of the room, provided that
           with minimal obstructions such as vent pipes, conduit, or  the mezzanine meets all of the following requirements:
           mechanical equipment.                                   1. Except for enclosed closets and bathrooms, the mez-
           R324.6.2 Setback at ridge. For photovoltaic arrays occu-  zanine is open to the room in which such mezzanine
           pying not more than 33 percent of the plan view total roof  is located.
           area, not less than an 18-inch (457 mm) clear setback is  2. The opening to the room is unobstructed except for
           required on both sides of a horizontal ridge. For photovol-  walls not more than 42 inches (1067 mm) in height,
           taic  arrays  occupying  more  than  33  percent  of  the  plan  columns and posts.
           view  total  roof  area,  not  less  than  a  36-inch  (914  mm)
           clear  setback  is  required  on  both  sides  of  a  horizontal  3. The exceptions to Section R325.5 are not applied.
           ridge.                                             R325.4 Means of egress. The means of egress for mezzanines
              R324.6.2.1  Alternative  setback  at  ridge.  Where  an  shall comply with the applicable provisions of Section R311.
              automatic  sprinkler  system  is  installed  within  the  R325.5  Openness.  Mezzanines  shall  be  open  and  unob-
              dwelling  in  accordance  with  NFPA  13D  or  Section  structed  to  the  room  in  which  they  are  located  except  for
              P2904, setbacks at ridges shall comply with one of the  walls not more than 36 inches (914 mm) in height, columns
              following:                                      and posts.
                1. For photovoltaic arrays occupying not more than  Exceptions:
                   66 percent of the plan view total roof area, not  1. Mezzanines or portions thereof are not required to be
                   less than  an  18-inch  (457  mm)  clear  setback  is  open to the room in which they are located, provided
                   required on both sides of a horizontal ridge.     that the aggregate floor area of the enclosed space is
                2. For photovoltaic arrays occupying more than 66    not greater than 10 percent of the mezzanine area.
                   percent of the plan view total roof area, not less  2. In buildings that are not more than two stories above
                   than a 36-inch (914 mm) clear setback is required  grade plane and equipped throughout with an auto-
                   on both sides of a horizontal ridge.
                                                                     matic  sprinkler  system  in  accordance  with  Section
              R324.6.2.2  Emergency  escape  and  rescue  opening.   R313, a mezzanine shall not be required to be open to
              Panels and modules installed on dwellings shall not be  the room in which the mezzanine is located.





         86                                                                  2018 INTERNATIONAL RESIDENTIAL CODE  ®
  Copyrighted © 2017 by, or licensed to, ICC (ALL RIGHTS RESERVED); licensed to UL, LLC pursuant to License Agreement with ICC. No further reproductions authorized or distribution authorized.
  ANY UNAUTHROIZED REPRODUCTION OR DISTRIBUTION IS A VIOLATION OF THE FEDERAL COPYRIGHT ACT AND THE LICENSE AGREEMENT; AND SUBJECT TO CIVIL AND CRIMINAL PENALTIES THEREUNDER.
   106   107   108   109   110   111   112   113   114   115   116