SANITARY DRAINAGE



                3. The size of cleanouts for cast-iron piping can be  P3005.2.10.1 Cleanout plug trim covers. Trim covers
                   in accordance with the referenced standards for  and access doors for cleanout plugs shall be designed
                   cast iron fittings as indicated in Table P3002.3.  for such purposes. Trim cover fasteners that thread into
           P3005.2.6 Cleanout plugs. Cleanout plugs shall be cop-  cleanout  plugs  shall  be  corrosion  resistant.  Cleanout
           per  alloy,  plastic  or  other  approved  materials.  Cleanout  plugs shall not be covered with mortar, plaster or any
           plugs  for  borosilicate  glass  piping  systems  shall  be  of  other permanent material.
           borosilicate glass. Copper-alloy cleanout plugs shall con-  P3005.2.10.2 Floor cleanout assemblies. Where it is
           form to ASTM A74 and shall be limited for use only on   necessary to protect a cleanout plug from the loads of
           metallic piping systems. Plastic cleanout plugs shall con-  vehicular  traffic,  cleanout  assemblies  in  accordance
           form to the referenced standards for plastic pipe fittings as  with ASME A112.36.2M shall be installed.
           indicated in Table P3002.3. Cleanout plugs shall have a  P3005.2.11 Prohibited use. The use of a threaded clea-
           raised square head, a countersunk square head or a coun-  nout opening to add a fixture or extend piping shall be pro-
           tersunk slot head. Where a cleanout plug will have a trim  hibited  except  where  another  cleanout  of  equal  size  is
           cover screw installed into the plug, the plug shall be manu-  installed with the required access and clearance.
           factured with a blind end threaded hole for such purpose.
                                                              P3005.3  Horizontal  drainage  piping  slope.  Horizontal
           P3005.2.7 Manholes. Manholes and manhole covers shall  drainage piping shall be installed in uniform alignment at uni-
           be of an approved type. Manholes located inside of a build-  form slopes not less than  /  unit vertical in 12 units horizon-
                                                                                   1
                                                                                    4
           ing  shall  have  gas-tight  covers  that  require  tools  for  tal (2-percent slope) for 2 /  inch (64 mm) diameter and less,
                                                                                   1
                                                                                    2
           removal.                                           and not less than  /  unit vertical in 12 units horizontal (1-per-
                                                                            1
                                                                             8
           P3005.2.8  Installation  arrangement.  The  installation  cent slope) for diameters of 3 inches (76 mm) or more.
           arrangement of a cleanout shall enable cleaning of drain-  P3005.4 Drain pipe sizing. Drain pipes shall be sized accord-
           age piping only in the direction of drainage flow.  ing to drainage fixture unit (d.f.u.) loads. The size of the drain-
              Exceptions:                                     age piping shall not be reduced in size in the direction of flow.
                1. Test tees serving as cleanouts.            The following general procedure is permitted to be used:
                                                                 1. Draw an isometric layout or riser diagram denoting fix-
                2. A two-way cleanout installation that is approved
                   for  meeting  the  requirements  of  Section    tures on the layout.
                   P3005.2.3.                                    2. Assign d.f.u. values to each fixture group plus individ-
           P3005.2.9 Required clearance. Cleanouts for 6-inch (153  ual fixtures using Table P3004.1.
           mm) and smaller piping shall be provided with a clearance  3. Starting  with  the  top  floor  or  most  remote  fixtures,
           of not less than 18 inches (457 mm) from, and perpendicu-  work downstream toward the building drain accumu-
           lar  to,  the face of the  opening  to  any  obstruction.  Clea-  lating  d.f.u.  values  for  fixture  groups  plus  individual
           nouts  for  8-inch  (203  mm)  and  larger  piping  shall  be  fixtures for each branch. Where multiple bath groups
           provided with a clearance of not less than 36 inches (914  are being added, use the reduced d.f.u. values in Table
           mm) from, and perpendicular to, the face of the opening to  P3004.1, which take into account probability factors of
           any obstruction.                                        simultaneous use.
           P3005.2.10 Cleanout access. Required cleanouts shall not  4. Size branches and stacks by equating the assigned d.f.u.
           be installed in concealed locations. For the purposes of this  values to pipe sizes shown in Table P3005.4.1.
           section, concealed locations include, but are not limited to,
           the  inside  of  plenums,  within  walls,  within  floor/ceiling  5. Determine the pipe diameter and slope of the building
                                                                   drain  and  building sewer  based  on  the  accumulated
           assemblies,  below  grade  and  in  crawl  spaces  where  the  d.f.u. values, using Table P3005.4.2.
           height from the crawl space floor to the nearest obstruction
           along the path from the crawl space opening to the cleanout  P3005.4.1 Branch and stack sizing. Branches and stacks
           location is less than 24 inches (610 mm). Cleanouts with  shall be sized in accordance with Table P3005.4.1. Below
                                                                                                 1
           openings at a finished wall shall have the face of the open-  grade drain pipes shall be not less than 1 /  inches (38 mm)
                                                                                                  2
                           1
           ing located within 1 /  inches (38 mm) of the finished wall  in diameter. Drain stacks shall be not smaller than the larg-
                             2
           surface. Cleanouts located below grade shall be extended to  est horizontal branch connected.
           grade level so that the top of the cleanout plug is at or above  Exceptions:
           grade. A cleanout installed in a floor or walkway that will  1. A 4-inch by 3-inch (102 mm by 76 mm) closet
           not have a trim cover installed shall have a counter-sunk    bend or flange.
           plug installed so the top surface of the plug is flush with the
           finished surface of the floor or walkway.                 2. A 4-inch (102 mm) closet bend connected to a 3-
                                                                        inch (76 mm) stack tee shall not be prohibited.









         670                                                                 2018 INTERNATIONAL RESIDENTIAL CODE  ®
  Copyrighted © 2017 by, or licensed to, ICC (ALL RIGHTS RESERVED); licensed to UL, LLC pursuant to License Agreement with ICC. No further reproductions authorized or distribution authorized.
  ANY UNAUTHROIZED REPRODUCTION OR DISTRIBUTION IS A VIOLATION OF THE FEDERAL COPYRIGHT ACT AND THE LICENSE AGREEMENT; AND SUBJECT TO CIVIL AND CRIMINAL PENALTIES THEREUNDER.
   690   691   692   693   694   695   696   697   698   699   700