Page 12 - DMEA Week 40 2021
P. 12

DMEA                                            REFINING                                               DMEA


       NNPC updates on Port




       Harcourt revamp progress




        AFRICA           THE  Nigerian National Petroleum Corp.   The Italian company had carried out a 50mn,
                         (NNPC) this week provided an update on work  six-month ‘integrity check’ in 2019 with fellow
                         to rehabilitate the country’s largest refinery com-  Italian firm Eni contracted as technical adviser.
                         plex, which is expected to resume almost full  This work included equipment inspection at the
                         operations by 2023.                  site, as well as “relevant engineering and plan-
                           In a statement, managing director Mele Kyari  ning activities”.
                         said that Italian engineering, procurement and   Speaking at a technical kick-off meeting at
                         construction (EPC) contractor Maire Tecni-  the PHRC complex in Alesa Eleme, Rivers State
                         mont is proceeding with work to return the Port  NNPC executive director for refineries and pet-
                         Harcourt Refining Co. (PHRC) to 90% of its  rochemicals Mustapha Yakubu said: “Everything
                         nameplate 210,000 barrel per day (bpd) capacity  has been put in place to ensure that the project
                         during the timeframe.                is delivered hitch-free and on schedule,” noting
                           Repairing the old refinery, known as Area 5,  that the facility will return to at least 90% capac-
                         is the first part of the plan to allow first refined  ity when it resumes operation.
                         products to be delivered by September next year.  Meanwhile, NNPC’s head of public affairs,
                           “We are happy we have the contractor on  Kennie Obateru told Punch daily in August that
                         board. With the strong collaboration of all par-  Tecnimont had already mobilised workers to the
                         ties involved, we will achieve the desired results,”  site. “The work is progressing,” he said. “We said
                         Kyari said.                          it will be completed within 18 to 44 months when
                           He added: “We have both government and  counting from April this year. By 18 months,
                         private sector financing. We have the Finance  some parts of the refinery will be producing. The
                         Ministry, NEITI, labour unions and other stake-  total rehabilitation job will be completed in 44
                         holders on board this project.”      months.”
                           The $1.5bn EPC was awarded to Maire Tecni-  NNPC’s entire 445,000 bpd refining capacity
                         mont in April following the agreement of a $1bn  has been shut in for nearly two years following
                         loan from Cairo-based African Export-Import  failure to carry out appropriate turnaround
                         Bank (Afreximbank) in February.      maintenance (TAM) for four decades.™













































       P12                                      www. NEWSBASE .com                        Week 40   07•October•2021
   7   8   9   10   11   12   13   14   15   16   17