Page 12 - DMEA Week 10 2021
P. 12

DMEA                                            REFINING                                               DMEA


       Angola to name winner of Soyo




       refinery contract on March 15




        AFRICA           ANGOLA’S Ministry of Mineral Resources and  private investment law had made it “necessary
                         Petroleum (MIREMPET) is slated to name the  to hold additional clarification meetings with
                         winner of a tender for the construction of a new  competitors.”
                         refinery in Soyo early next week, on March 15.  As of late December, MIREMPET had
                           MIREMPET wrapped up the bidding process  received nine final bids for the refinery contract
                         for the contract, which envisions the building a  and had named the bidders: Atis Nebest-Angola,
                         100,000 barrel per day (bpd) oil-processing plant  a local firm; China Petroleum Pipeline (CPP);
                         in Angola’s Zaire Province, in late December. It  Gemcorp Capital (UK); Jiangsu Sinochem Con-
                         had originally planned to select the winner of the  struction Co. (China); Quanten Consortium
                         tender before the end of 2020 but the deadline  (US); SDRC (China); Satarem (Switzerland);
                         was pushed back twice, first to March 1 and then  Tobaka Investment Group (South Africa), and a
                         to March 15.                         consortium formed by China National Machin-
                           The ministry justified the first postponement  ery & Equipment Import & Export Corporation
                         by saying that the potential investors needed to  (CMEC) and two relatively unknown compa-
                         review their guarantees for investment financ-  nies, AIDA and VSF.
                         ing. It said in a statement at the time that the   Since then, one of the bidders has dropped
                         bidders would have to work “through renowned  out of the contest. MIREMPET has not yet iden-
                         financial institutions, as well as [re-affirm] the  tified the entity in question, but it has indicated
                         corporate structures involved” for this part of  that all of the other eight have completed the due
                         the process.                         diligence process carried out by its contractor,
                           Then last week, it explained that it had put  PricewaterhouseCoopers (PwC).
                         off the announcement yet again at the request of   The ministry began accepting bids for the
                         some of the bidders.                 project early last year and had hoped to declare
                           After the presentation of the ministry’s pre-  the winning contractor in April. However, it
                         liminary report, it said, “some competitors  was forced to change the timeline for the tender
                         asked the evaluation committee for additional  because of the coronavirus (COVID-19) pan-
                         information, demanding time for due [dili-  demic, which slowed the process of making the
                         gence].” Additionally, it stated that Angola’s  necessary evaluations and adjudications.™












































       P12                                      www. NEWSBASE .com                         Week 10   11•March•2021
   7   8   9   10   11   12   13   14   15   16   17