Page 9 - MEOG Week 42 2021
P. 9

MEOG                                  PROJECTS & COMPANIES                                            MEOG


       Contract awarded as Turkey




       pushes for Sakarya development




        TURKEY           US oilfield services specialist Schlumberger this  subsea equipment, a monoethylene glycol
                         week announced that it had been awarded a con-  (MEG) injection pipeline and 170 km of gas
                         tract as part of a consortium by Turkish Petro-  export pipelines connecting to the port of Filyos,
                         leum (TPAO) for work on the offshore Sakarya  where the foundations of a gas processing facility
                         gas field.                           were laid in June.
                           The news comes as the country’s energy and   TPAO discovered 320 bn cubic metres of gas
                         natural resources ministry anticipates the field  at Tuna-1 in August last year, which was subse-
                         commencing commercial production in 2023  quently upgraded to 405 bcm two months later
                         and providing around a third of Turkish natural  and renamed Sakarya. In early June, the com-
                         gas demand by 2027. Meanwhile, the contract  pany announced that it had found another 135
                         covers the final part of the project’s midstream  bcm with the Asmara-1 well, taking the total
                         section, which will tie the field to processing  volume discovered so far at Sakarya to 540 bcm.
                         facilities on the Zonguldak coast and connection   TPAO has been carrying out a 10-well drill-
                         to the country’s gas grid.           ing campaign designed to achieve first gas and
                           Schlumberger and Luxembourg-registered  3.65 bcm per year by 2023 and a further 30 wells
                         Subsea 7 were awarded an engineering, pro-  will be drilled to reach an annual plateau of 15
                         curement, construction and installation (EPCI)  bcm by 2025. Local media have begun quoting
                         of end-to-end production solutions for Sakarya.  an anticipated flow rate of 5-10 bcm in 2023,
                           According to Schlumberger, the project scope  though no explanation for the increase has been
                         covers subsurface solutions to onshore produc-  provided.
                         tion, including well completions, subsea pro-  Under the drilling programme, the Fatih
                         duction systems (SPS), subsea umbilicals, risers,  drillship began work on the Turkali-5 well in
                         flowlines (SURF) and an early production facil-  mid-September, following the successful com-
                         ity (EPF).                           pletion of the Tuna1-, Turkali-1, 2, 3 and 4, and
                           The American firm will carry out the well  Asmara-1 wells.
                         completions’ scope and the design, construction   In August, TPAO lit the first gas flare at the
                         and commissioning of the early production facil-  new field and performed the first flow test at Tur-
                         ity, which it said would be capable of handling  kali-2. That well flowed at 22 mmcf (0.623 mcm)
                         350mn cubic feet (9.9mn cubic metres) per day  per day, less than the 26.5 mmcf (0.75 mcm) per
                         of gas. Meanwhile, the SPS and SURF systems  day recorded in July during a test which sug-
                         will be delivered by Schlumberger and Subsea 7’s  gested the reservoir could flow at around 42.5
                         subsea technologies, production and processing  mmcf (1.2 mcm per day).
                         systems division OneSubsea.            Another drillship, the Kanuni, which carried
                           This covers the provision and installation of  out completions at Turkali-2, is working on a
                         infield flowlines, tie-in connections, associated  third production test at the well.™


































       Week 42   20•October•2021                www. NEWSBASE .com                                              P9
   4   5   6   7   8   9   10   11   12   13   14