Page 12 - DMEA Week 18 2021
P. 12

DMEA                                            REFINING                                               DMEA


       South Pars 14 refinery




       to be complete by July




        MIDDLE EAST      IRAN is closing in on the completion of the gas  holds ultimate responsibility for the projects,
                         refinery dedicated to Phase 14 of the supergiant  with fellow National Iranian Oil Co. (NIOC)
                         South Pars field, as it nears commissioning of all  subsidiary Petropars carrying out jobs on the
                         phases associated with the asset.    surface and subsurface. The only phases still to
                           The local Pars Oil and Gas Co. (POGC)  be completed are the Phase 14 refinery and the
                         announced this week that the first train of the  offshore Phase 11 for which Total previously held
                         Phase 14 refinery will be completed and ready  a contract with NIOC.
                         for commissioning on schedule in early July.   In February, Meshkinfam said that by March
                         The company’s managing director, Mohammad  20, the end of the Iranian calendar year, “the
                         Meskinfam, said it “will be handed over to the  development … will be nearly completed and we
                         commissioning group in early July this year, and  will not have any work left except for Phase 11 in
                         then the commissioning activities will continue  the offshore sector and the refinery of Phase 14
                         to prepare the different units of this train for  in the onshore sector; which will be operational
                         operation”.                          early next year.”
                           “Fortunately, with the follow-ups done, the   Iran is home to around 34 trillion cubic
                         ancillary units of Phase 14 of South Pars are now  metres of proven natural gas reserves, with
                         ready for commissioning, and in the process  South Pars accounting for around 14 tcm as well
                         section, the reception facilities will be ready to  as 18bn barrels of gas condensates.
                         receive gas by late May,” he added.    The Islamic republic holds a 3,700-square
                           South Pars is split into 24 offshore develop-  km portion of the 9,700-square km deposit that
                         ment phases and 14 onshore gas refineries which  is shared with Qatar, where it is known as the
                         process the gas produced offshore. POGC, a sub-  North Dome field. Around 80% of the field’s ini-
                         sidiary of the National Iranian Oil Co. (NIOC),  tial gas reserves are believed to remain in place.™