Page 6 - NorthAmOil Week 28 2022
P. 6

NorthAmOil                             PIPELINES & TRANSPORT                                      NorthAmOil














































       Court upholds Nexus




       pipeline approval






        US               THE US Court of Appeals for the District of  capacity to re-import the gas into New York and
                         Columbia (DC) Circuit last week upheld the Fed-  New England after it has transited Canada.
                         eral Energy Regulatory Commission’s (FERC)   The Nexus pipeline is operated by Enbridge,
                         approval of the already operational Nexus Gas  which built it in a 50:50 partnership with DT
                         Transmission pipeline. The pipeline carries gas  Midstream, and covers a distance of 256 miles
                         from Appalachia to the Midwest, from where it  (412 km), with a capacity of 1.5bn cubic feet
                         is exported to Canada.               (42.5mn cubic metres) per day. The pipeline
                           A challenge against the approval had been  entered service in 2018 but the City of Oberlin
                         filed by the City of Oberlin, Ohio, but the court  has continued its efforts to challenge its approval
                         found that the FERC had acted appropriately  in the courts. This is part of a growing trend of
                         when it approved the project. This comes after  challenges against pipelines that continue even
                         the city tried to argue in part that the regulator  after those pipelines have become operational.
                         should not have considered demand for gas  Thus far, though, efforts to shut down exist-
                         bound for export when assessing the public need  ing oil and gas pipelines in the US have been
                         for the project.                     largely unsuccessful, though some fights remain
                           However, the court disagreed, ruling that it  ongoing.
                         was reasonable for the FERC to deem gas being   Meanwhile, ClearView Energy Partners
                         exported to a free-trade country such as Canada  has commented that the DC Circuit’s ruling
                         to be in the public interest. It also agreed with the  on Nexus might influence the FERC’s deci-
                         regulator that building additional capacity for  sion-making on future interstate gas pipeline
                         export to the Dawn Hub in Ontario, Canada has  projects for which export demand would be a
                         domestic benefits, including by creating more  consideration.™







       P6                                       www. NEWSBASE .com                           Week 28   15•July•2022
   1   2   3   4   5   6   7   8   9   10   11