Page 13 - GLNG Week 20 2021
P. 13

GLNG                                              ASIA                                                GLNG


       Stena wins FEED contract for




       Vietnamese LNG project




        PROJECTS &       STENA  Power & LNG Solutions has been  detailed model testing to ensure optimum per-
        COMPANIES        awarded a front-end engineering and design  formance under the environmental conditions
                         (FEED) contract for the use of its jettyless LNG  in the Mekong Delta, Stena said.
                         transfer and regasification technology at Delta   “The Jettyless Floating Terminal and the
                         Offshore Energy’s (DeltaOE) planned LNG-to-  Self-Installing Regas Platform are key compo-
                         power project in Vietnam.            nents of our LNG-to-power solution for Bac
                           This builds on a technology licence agree-  Lieu,” stated DeltaOE’s managing director,
                         ment reached between the two companies from  Bobby Quintos. “They allow us to position the
                         August 2020 for DeltaOE to use Stena’s jettyless  LNG receiving terminal offshore, and thereby to
                         technology.                          minimise the project’s impact on land and on the
                           DeltaOE’s project, which is located in Bac  coastline of Bac Lieu,” he added.
                         Lieu Province in southern Vietnam, is set to   “Our jettyless LNG-to-power technology has
                         be among the country’s first privately operated  been created to meet demand for more flexible
                         regasification terminals. The power plant will  LNG import and export terminals, such as is
                         have a capacity of 3.2 GW, with DeltaOE aiming  required for the hugely exciting Bac Lieu LNG-
                         to bring the first 800-MW block online by early  to-power project,” Stena’s chief technology
                         2024 and to have all four blocks in service by the  officer, Svein Hellesmark, said.
                         end of that year. The company is targeting the   Several LNG-to-power projects have been
                         start of construction later this year.  proposed for Vietnam, but thus far only the Hai
                           DeltaOE will employ Stena’s Jettyless Floating  Linh terminal is thought to be near start-up,
                         Terminal (JFT) and Self-Installing Regas Plat-  while the state-backed Thi Vai terminal is
                         form (SRP) for the project. These will be located  under construction. Among the other projects,
                         roughly 40 km offshore. The FEED will include  DeltaOE’s scheme is among the frontrunners.™





                                                       EUROPE

       Equinor completes internal probe into fires





        PROJECTS &       NORWAY’S Equinor has completed its internal  concluded its own probe into the Hammerfest
        COMPANIES        investigation into two fires that broke out at its  LNG fire in late April, finding that dead insects
                         Hammerfest LNG plant and Tjeldbergodden  within five-year-old air-intake filters and heat
                         methanol facility last year, pledging to hire and  from anti-icing panels were behind the fire at
                         train more staff.                    one of the plant’s power turbines. The damning
                           The incidents were caused by both technical  report said there were serious breaches of regula-
                         and human errors, Equinor said on May 12. The  tions. It noted that Equinor had, as a cost-cutting
                         blaze at Hammerfest LNG happened last Sep-  measure, changed its maintenance schedule for
                         tember, resulting in an 18-month expected out-  air filters from annual replacements to inspec-
                         age, while the fire at the methanol plant occurred  tion-based maintenance. The filters in question
                         in early December and led to two months of  had not been replaced in six years.
                         downtime.                              Equinor disputed that filter maintenance was
                           “We are bolstering our recruitment of engi-  a contributing factor, however.
                         neering resources within electrical disciplines   “The investigation group does not believe
                         and up to 50 skilled workers are bound for the  that the maintenance interval for exchanging the
                         onshore facilities,” Equinor said in a statement.  filters that self-ignited is a contributing cause,”
                         The company has faced repeated calls from  the company said.
                         labour units to increase staff and training.  No one was injured in the incident, and
                           While the incident at Tjeldbergodden was  Equinor said there was no major risk of personal
                         the result of a runaway steam turbine after its  injuries. Both the company and the PSA con-
                         shutdown valve malfunctioned, the self-ignition  cluded that the fire was unlikely to have spread
                         of filters in an air intake at the LNG plant was  to other parts of the facility.
                         caused by several “direct and underlying factors.”  The PSA is yet to publish its findings on the
                           Norway’s Petroleum Safety Authority (PSA)  methanol fire.™



       Week 20   21•May•2021                    www. NEWSBASE .com                                             P13
   8   9   10   11   12   13   14   15   16   17   18