Implementation
Before the commencement of work, we conducted a
comprehensive risk assessment and submitted necessary
work permits to the campus facilities management team.
This ensured that all safety protocols were in place before
proceeding with the installation.
The actual installation of the units took place in October
2024. Following this, we set up a monitoring system to ensure
seamless data transmission and real-time status updates.
Figure 13 Implementation (Power supply, solar panel, monitoring)
Figure 12 Record-taking
Figure 14 Implementation (Designing, Mobile display*,
Machine display*)
*Adopted from SG Recycling