Page 25 - Rosendin_Q2_2019_Newsletter
P. 25

reviously, a linear process involved  FROM VALUE CHAIN TO SUPPLY CHAIN  Admins on a job site, for instance,
            a consultant working with a client   Hyperscale providers have moved   shouldn’t have to fill out forms. That’s
       Pwho called out the needs of the       the design and build process from    not efficient, rewarding or impactful.
        business. The consultant would put    transactional to strategic because
        together a rough design, typically    the operations therein are core to   Some manufacturers and contractors
        around the worst-case scenario and    the business and critical to meeting   are integrating an “Uber approach”
        largest hardware footprint. The design   the ever-increasing expectations   as another means of addressing
        would be put out to RFP and, generally   of the digital world. As the market   capacity constraints, a tighter labor
        speaking, the lowest bidder won.      has outpaced vendors’ capacity to    pool and their inability to bring
                                              manufacture and construct against it,   new manufacturing facilities on-line
        Now, it’s table stakes for manufacturers  the industry is playing catchup.  expediently. This method leverages
        to participate in that process and    Still, as demand continues to increase   other third-party partners to
        ever more important for the entire
                                                                                   supplement their own capacity; for
 HYPERSCALE'S IMPACT  “value chain” — vendors, consultants,   and the labor scarcity grows, the   example, employing smaller builders
                                                                                   that can more easily meet spot spikes.
        builders, contractors, integrators, etc.
                                              product stream remains constricted.
                                              To address this obstacle, some
                                                                                   Third-party integrators fall into this
        — to work together up front, in a more
                                              manufacturers are establishing
        open way. A lack of coordination leads
                                                                                   category as well.
 ON DATA CENTER BUILD AND DESIGN:  to inefficiency, an obvious deterrent to   dedicated capacity for the hyperscale   Streamlining the supply chain process
                                              segment so as not to interrupt the
        speed. Minimizing inefficiency requires
        a more collaborative approach. The
                                                                                   with prefabricated solutions and
                                              flow of their core businesses. After
                                                                                   auxiliary providers will hasten delivery
         higher the demand, the faster the
                                              all, construction in other key building
 CALLING ALL PLAYERS TO THE TABLE  need to deploy, and the more   sectors is still growing — albeit at less   and get hyperscale data centers up and
                                                                                   running in the field faster. Reinventing
             connected stakeholders need to
                                              of a steep curve.
                                                                                   such practices also depends on higher
               be. In the end, it’s shuffling
                 the sequence and then        But this approach alone won’t be     collaboration. Together, the value
                 overlapping several activities   enough. The hyperscale paradigm   chain stakeholders must determine
                that had been traditionally   combined with resource constraints is   what can and should be done in which
             serially sequenced.              dictating a new approach to the entire   environment and how; at the fastest
 By Bill Mazzetti and Frank Nash | Reprinted from 7x24 Exchange International  supply chain. For one, standardization   possible pace at the most reasonable
        Such huge demand for speed and        in the form of prefabricated solutions   price.
        scale also means that cost may not be   can help eliminate the need for custom
        the top consideration in deployments   engineering and reduce on-site man-  THE PAST IS NOT SUSTAINABLE
        any longer. Traditional procurement   hour requirements, as well as baseline   The way it was ‘always done’ will not
        methods, where purchasers make        schedule and project assumptions     lead to successful design and build of
        decisions primarily based on price but   by all on-site participants. This is the   hyperscale data centers. To compete,
        are mostly removed from the reality   paradigm shift from the top-down     it’s time to break habits in place since
        of the business case, is becoming     approach that has been tradition for   the 1970s. Purchase, bid, evaluate
        obsolete. Considering the time frame   decades.                            and contract is a thing of the past and
 The demand for   principals in this industry have been                            a linear, engineering approach will
 megawatt tonnage   operating, hardware and construction   Pre-integration and testing in a   cost more and take longer to deploy
                                              controlled manufacturing environment
        costs are well-known. This knowledge
                                                                                   in this exploding market sector. This is
 from the big five' cloud   should allow organizations to baseline   enables not just speed to market but   no different than the past two major
        deployment and purchasing decisions
                                                                                   paradigm shifts in the data center
                                              also higher reliability. Data Center
 providers, coupled with service   as opposed to resorting to a pure RFP-  facilities are subjected to rigorous   industry – the Tier/Class grading
        based purchasing exercise.
                                              commissioning exercises. Assembling
                                                                                   system where none previously existed,
 providers pursuing market share, is   Rather, resources and scheduling   and testing components and hardware   rendering measurable standards for
                                                                                   data center facilities; and the data
                                              sub-assemblies as well as integrating
 unprecedented. The five majors are driving   are the new priorities as a skilled   monitoring systems, can be done   center real estate solutions that
                                                                                   productized those assumptions, while
                                              partially or fully in a factory, avoiding
        labor shortage is jeopardizing the
 extraordinary scale at record speed, not only   ability to meet project schedules. In   the need for valuable labor on site.  transferring financial and operational
 constructing their own data centers, but also leasing   the electrical contractor field alone,   Ideally, and especially during times   responsibilities to service providers.
        the National Electrical Contractor’s
                                                                                   This dynamic is no different. It’s merely
 out huge chunks of infrastructure and space. Traditional   Association (NECA) research predicts   of constrained capacity, workers can   the next frontier in the chase for
                                              perform to the highest level of their
        the need for 300,000 more electricians
                                                                                   efficiency. Integrated project delivery is
 data center construction methods are being upended. In this   between now and 2025 — a far   skillsets for the longest time every day.   that new model. It brings all players to
        greater number than currently on that
                                              That is, in part, what prefabricated
                                                                                   the table with a standardized process
 new data center design and build paradigm, all the players must   intended career path.  solutions enable. What can be   for optimized results.
                                              automated should be automated.
 come to the table to collaborate for success.