Page 27 - Q4_2021_Corp Newsletter
P. 27

PRACTICAL STEPS YOU CAN TAKE TO ADDRESS
        CHALLENGES AND ENSURE CODE COMPLIANCE



        Below are some practical steps to understand the
        topology issues and select and purchase overcurrent
        devices and gear that comply with Code.
           1.     Determine which Code Version the AHJ enforces
              for the project and/or is specified by the Engineer
              of Record (EEOR). The Code Version can be
              determined by contacting the Project Manager or
              through an RFI to the EEOR if it is not specified in the
              contract documents. The possible answers will be NEC
              requirements to 10ms (full range of Current and Time)
              or CEC (or AHJ) acceptance to 100ms (0.1 seconds).

           2.     In reviewing the Single Line Diagram look for cases where
              there are more than four panels or distribution boards from
              the furthest branch circuit panelboard to the main switchboard.
              If this is the case, the system will have difficulty fully coordinating
              due to the number of layers of overcurrent devices in series.
 THE CHALLENGE OF    3.    If there are more than three panels or distribution boards from the furthest
              branch circuit panelboard to the generator, the system will have difficulty fully
              coordinating due to the number of layers of overcurrent devices in series.
 SELECTIVE COORDINATION  4.    To achieve full coordination systems with circuit breakers, we need
              frame sizes between four and six TIMES the downstream circuit
              breaker, which means a 100A panel with Main Circuit Breaker must
 By Ron Wilson, P.E., VP of Engineering  be fed from a 400A distribution panel with the main breaker. If this
              is not the case, Coordination will be challenging to achieve.
 he issue of Selective Coordination of Emergency and Elevator Systems has become an   5.     If magnetic circuit breakers are installed in series, they will rarely
 increasingly challenging issue over the past several years. Each project that Rosendin bids,   coordinate unless the frame sizes for the upstream circuit
              breakers are 4X to 6X that of the downstream breakers.
 Tas well as any project we design, must address the issue of Selective Coordination in the
           6.     Systems with risers that tap to panels of the same size main circuit
 Emergency Systems (Article 700), Legally Required Standby Systems (Article 701), Critical Operation   breaker will not fully coordinate, so risers must provide feeds
 Power Systems (Article 708), and Elevator Systems (Article 620). Most design engineers and   to a distribution panel that sub feeds lower sized panels.
 estimating and purchasing agents are unaware of the requirements and often do not understand   Since most design engineers are not fully up to speed on the
        Selective Coordination requirements, most designs produced
 the ramifications. Our teams have been dealing with this issue on projects, and it can regularly cost
        for bid may not address the issue of Selective Coordination. The
 over $100K to implement the requirements for Selective Coordination. In addition, the electrical   electrical contractor is still expected to comply with the Code
 topology may need to change along with physical equipment. This change can add to the equipment   regardless of the design. Also, while equipment vendors are aware
        of Selective Coordination requirements, they will rarely account for it
 cost and delay project delivery if not addressed during the design and procurement phases.  in a bid as it adds cost. Finally, many jurisdictions are becoming aware
        of the Selective Coordination requirement. Still, they may not catch
        it in plan check, but the field inspector may ask the question causing
 WHAT IS SELECTIVE COORDINATION?  increased challenges affecting cost and schedule during construction.



 Selective Coordination is the ability for the overcurrent   The 2014 NEC and 2016 CEC requirements, and later   HOW CAN I BE SURE WE ADDRESSED SELECTIVE COORDINATION?
 devices (circuit breakers and fuses) in an electrical   versions, now require breakers and fuses to provide localized
 distribution system to coordinate such that the overcurrent   fault clearing when designing distribution topologies and
 protective device closest to a fault clears the fault rather   selecting actual breakers from manufacturers. We must   For more information and questions, contact the Engineering
 than upstream devices that could affect a more significant   first determine if the Selective Coordination will need   Department. Visit the Engineering HELPDESK page on Rosendin’s
 portion of the electrical distribution. This ability is of   to meet NEC or CEC requirements (CEC if the project is   intranet, call 1.833.734.3647, or email REIEngr@rosendin.com.
 particular concern with emergency systems as they are relied   within a California Jurisdiction). The NEC requires selective
 upon during emergency conditions to provide critical life   Coordination down to 10mS (0.01sec), whereas CEC requires   For RFIs regarding the selective coordination expectation during the bid process,
 safety power that allows people to exit a facility safely.   (or by lack of clarification within the definition, and stated   be sure the vendor provides a quote complying with Code Sections 700, 701, 708 &
    explicitly for OSHPD projects) down to 100mS (0.1sec).    620. Engineering can provide language to include with the quote request to help. 


 26  |  THE FEEDER                                                                                  THE FEEDER  |  27
   22   23   24   25   26   27   28   29   30   31   32