Page 23 - PENYIASATAN TAPAK
        P. 23
     1. PRELIMINARIES
                 3.   Work Program
                      •     The Contractor shall plan the execution of the works by preparing a work
                            program and submitting it for approval by the S.O.
                      •     The work program will be used by the S.O. to monitor progress and be the
                            basis for the assessment of extensions of time.
                 4.   Supervision of works
                      •     To    appoint      Professional      Engineer       with    Practicing      Certificate      (PEPC)/
                            Professional Geologist (P.GEOL) for monitoring and standing supervision on site
                            and laboratory including endorsing the SI report.
                      •     The PEPC/ P.GEOL may appoint a qualified representative on his behalf to carry
                            out monitoring and supervision subject to S.O. approval.
                      •     The PEPC/ P.GEOL and representatives must fulfill the minimum requirements as
                            specified by the S.O.
     	