Page 26 - PENYIASATAN TAPAK
        P. 26
     1. PRELIMINARIES
                 5.   Setting out
                      •    Setting out shall be carried out by a licensed surveyor, including the taking of
                           reduced levels and the coordinates of all testing locations in RSO and Cassini
                           format based on the established benchmarks.
                      •    If there are no established benchmarks available, a temporary benchmark or
                           level obtained from a nearby land or road level shall be taken as a reference
                           point and transferred to the proposed site using suitable survey method.
                      •    The reduced level shall not be obtained by interpolating contour lines on the site
                           plan.
                 6.   Temporary Access
                      •     The Contractor is responsible for providing temporary roads and accesses
                            required for the proper execution of the works for the site located in RURAL or
                            REMOTE area.
     	