Page 16 - How do I Setup a LOC NON_LOC and PREPAID Contracts
P. 16
Setting up a LOC NONLOC and PREPAID Contracts
K. Quality Check.
1
1. Click the Approve button.
In Progress stamp changes to Approved and date/time stamp is updated with time Approved. Prop QC step changes to
Pending.
For detailed steps regarding any workflow action, refer to job aid How do I approve an Award Setup Request.
A quality check will need to be obtained before Activating the Contract. This person should NOT be the same
person who Approved at the Award stop. The approver can use any checklist and/or cheat sheets that are
available to verify that the information is correct on the Award/Contract before Activating the Contract.
The Quality Check Person should:
Mark the Request In Progress.
Quality Check all items.
Follow the steps outlined in Section L Contract Activation Process.
Approve final Step, Award QC, to complete the Workflow.
Page 16 of 22