Planning

            Status of Traffic Facility Works (Plan Head-1600)

            A.   Sanctioned Works
               I.  Works sanctioned under PWP/LSWP/umbrella works
                                                                                                             (Rs. in 000‟)
          S.   Work                          TDC     Current status                        Next step/Steps with
          No.                                                                              intermediate TDC
          a.   Janakampet:                 30.06.23  •   ESP Approved by HQ on 17.08.22.    •   SWR under preparation.
               Additional Loop Line                  •   Detailed Estimate vetted on        •   Tender opened on
               (Division)                               06.06.2022 and sanctioned on           05.07.2022, under
               Year of Sanction: 2021-22                10.06.2022.                            finalization.
                                                     •   Tentative SIP received on          •   Funds required in PH-
               Anticipated Cost: 11.30                  23.08.2022.                            16.
               Crs                                   •   S&T-Tender awarded
                                                     •   Engg-bridge extension work in     TDC:
                                                        progress.                            SWR-10.12.2022
                                                     •   SIP received on 19.09.2022.
                                                     •   SWRD prepared on 26.09.2022.
                                                     •   SWR pending with S&T Branch since
                                                        17.10.2022.


          b.   Falaknuma (PH-I):           31.07.23  •  Detailed Estimate vetted by Accounts     Work commenced at site.
               Provision of Down Loop                  on 06.06.22.                            Funds required in PH-16.
               Line (Division)                      •  Tender awarded on S&T-24.10.22,         SWR pending with S&T
                                                       Engg.-13.09.22, TRD-21.07.22,          Branch since 10.10.2022.
               Year of Sanction: 2021-22            •  ESP approved on 05.07.2022.
                                                    •  SIP approved on 01.08.2022.         TDC:
               Anticipated Cost: 8.57 Crs           •  TOC received on 10.08.2022.           SWR-10.12.2022
                                                    •  SWRD prepared on 24.09.2022.
                                                    •  SWR under checking.
          c.   Perur: New Crossing         31.03.23  •  Detailed estimates sanctioned on    •  Bridge extension - work
               Station Between WPR-                    19.03.2019.                           completed, Tender called
               KQQ (Division)                        •  ESP manually approved.               for Building portion and
               Year of Sanction: 2017-18             •  Approved SIP received on 25.04.2022.   opened on 28.06.22.
               Anticipated Cost: 8.80 Crs            •  TOC received on 02.05.2022.          Under finalization.
                                                     •  SWRD prepared on 12.05.2022.        •  Funds required in PH-16.
                                                    •  SWR prepared on 22.09.2022.          •  S&T works tender
                                                                                             awarded.

          d.   Jukal:                      31.03.23  •  ESP approved on 25.07.2022.      •  SWRD and SWR to be
               New Crossing Station               •  SIP  prepared  and  submitted  by  HQs  prepared by S&T branch.
               Between UR-TMX (RVNL)                 16.09.2022.
               Year of Sanction: 2010-11          •  SIP received on 03.10.2022.           TDC:
               Anticipated Cost: 16.95            •  SWRD & SWR not prepared.              SWRD-20.12.2022
               Crs                                •  Alt  1  ESP  for  interlocking  of  LC19   SWR-31.12.2022
                                                     cleared by division.
          e.   Alampur Road:               31.03.23  •  Work  transferred  to  Gati  Shakti  unit  on •  Work in progress by
               Yard Remodeling (Project)            13.10.2022.                             Construction Department.
                                                  •  ESP approved manually.               •  SIP pending with HQs.
                                                  •  SIP to be prepared by HQs.            TDC:
                                                  •  Request  for  alteration  in  SIP  sent  to  HQ  SIP-10.12.2022
                                                    on 28.10.22.                           TOC-12.12.2022
                                                                                           SWRD-15.12.2022
                                                                                             SWR-20.12.2022