Planning
Status of Traffic Facility Works (Plan Head-1600)
A. Sanctioned Works
I. Works sanctioned under PWP/LSWP/umbrella works
(Rs. in 000‟)
S. Work TDC Current status Next step/Steps with
No. intermediate TDC
a. Janakampet: 30.06.23 • ESP Approved by HQ on 17.08.22. • SWR under preparation.
Additional Loop Line • Detailed Estimate vetted on • Tender opened on
(Division) 06.06.2022 and sanctioned on 05.07.2022, under
Year of Sanction: 2021-22 10.06.2022. finalization.
• Tentative SIP received on • Funds required in PH-
Anticipated Cost: 11.30 23.08.2022. 16.
Crs • S&T-Tender awarded
• Engg-bridge extension work in TDC:
progress. SWR-10.12.2022
• SIP received on 19.09.2022.
• SWRD prepared on 26.09.2022.
• SWR pending with S&T Branch since
17.10.2022.
b. Falaknuma (PH-I): 31.07.23 • Detailed Estimate vetted by Accounts Work commenced at site.
Provision of Down Loop on 06.06.22. Funds required in PH-16.
Line (Division) • Tender awarded on S&T-24.10.22, SWR pending with S&T
Engg.-13.09.22, TRD-21.07.22, Branch since 10.10.2022.
Year of Sanction: 2021-22 • ESP approved on 05.07.2022.
• SIP approved on 01.08.2022. TDC:
Anticipated Cost: 8.57 Crs • TOC received on 10.08.2022. SWR-10.12.2022
• SWRD prepared on 24.09.2022.
• SWR under checking.
c. Perur: New Crossing 31.03.23 • Detailed estimates sanctioned on • Bridge extension - work
Station Between WPR- 19.03.2019. completed, Tender called
KQQ (Division) • ESP manually approved. for Building portion and
Year of Sanction: 2017-18 • Approved SIP received on 25.04.2022. opened on 28.06.22.
Anticipated Cost: 8.80 Crs • TOC received on 02.05.2022. Under finalization.
• SWRD prepared on 12.05.2022. • Funds required in PH-16.
• SWR prepared on 22.09.2022. • S&T works tender
awarded.
d. Jukal: 31.03.23 • ESP approved on 25.07.2022. • SWRD and SWR to be
New Crossing Station • SIP prepared and submitted by HQs prepared by S&T branch.
Between UR-TMX (RVNL) 16.09.2022.
Year of Sanction: 2010-11 • SIP received on 03.10.2022. TDC:
Anticipated Cost: 16.95 • SWRD & SWR not prepared. SWRD-20.12.2022
Crs • Alt 1 ESP for interlocking of LC19 SWR-31.12.2022
cleared by division.
e. Alampur Road: 31.03.23 • Work transferred to Gati Shakti unit on • Work in progress by
Yard Remodeling (Project) 13.10.2022. Construction Department.
• ESP approved manually. • SIP pending with HQs.
• SIP to be prepared by HQs. TDC:
• Request for alteration in SIP sent to HQ SIP-10.12.2022
on 28.10.22. TOC-12.12.2022
SWRD-15.12.2022
SWR-20.12.2022