f.   Nizamabad- Remodeling of             •  Work kept under abeyance, will be  •  ESP Pending with
                 yard arrangements for                  taken up after shifting of Goods   Dy.CE/PND since
                 providing additional                   Shed to JKM.                      30.11.2022.
                 platforms and one full length         •  ESP approved by DRM on        •  Funds required for Phase-
                 dead end spur. (Division)              26.09.2022 and sent to HQs on     II in PH-1600
                 Year of Sanction: 2018-19      --      06.10.2022 for approval.            TDC:
                 Anticipated Cost: 9.39 Crs                                                  ESP-10.12.2022
                                                                                             SIP-18.12.2022
                                                                                             TOC-20.12.2022
                                                                                             SWRD-24.12.2022
                                                                                          •  SWR-30.12.2022

              II.  Works sanctioned under GM‟s OOT
            S.   Work                          TDC     Current status                Next step/Steps with
            No.                                                                      intermediate TDC
             a.   Basar: Provision of Isolation    • Work proposed under GM‟s    •  SWRD/SWR by S&T branch to
                 (sand hump/ overshoot line)        OOT.                             be prepared.
                 for 2nd loop towards SC           • ESP approved by CE/PND on  •  TOC awaited from HQs.
                 end.                               08.08.22.                    •  S&T-Tender to be floated TDC
                 (Division)                        • IRPSM ID generated on          05.11.22
                                             28.02.23  07.09.2022.               •  Engg- Tender opening on
                 Year of sanction:                 • Detailed Estimates sanctioned   11.11.2022.SWR-24.12.2022
                 2022-23                            on 16.10.2022.
                                                   • SIP received & approved on
                 Anticipated cost:                  01.11.2022.
                 Rs.1.60 cr                        • SWRD & SWR not prepared.

                                                                                 •
             b.   Sitafalmandi A cabin:            •  Work  proposed  under  GM‟s   Detailed Estimates Sanctioned on
                 Conversion of UP loop line           OOT.                         19.10.22.
                                                                                 •
                 to Common loop.                   •  IRPSM    ID   generated   on   Grade condonation sent to HQ for
                 (Division)                           07.09.2022.                  approval.
                                                                                 •
                                                   •  ESP  approved  by  CE/P&D  on   SWRD & SWR by S&T branch to
                 Year of sanction:                    16.09.2022.                  be prepared.
                 2022-23                     30.05.23  •  SIP  received  on  17.10.2022, •  Tender Schedule (Engg, S&T,
                                                      under finalization at Division.   TRD) under preparation (TDC
                 Anticipated cost:                 •  SWRD & SWR not prepared.     08.11.22. 09.11.22, 09.11.22).
                 Rs. 2.18 cr                                                        TDC:
                                                                                    SIP-11.12.2022
                                                                                    SWRD-21.12.2022
                                                                                    SWR-29.12.2022


           III.  Works Proposal under Revenue:
            Sl.   Work                      TDC      Current status                   Next step/Steps with
            No.                                                                       intermediate TDC
            a.   Kacheguda:                       •  Work proposal uploaded under   •  SIP, SWRD & SWR Pending.
                 Proposal of Modifications to        OOT in IRPSM on 26.08.2022 and   TDC:
                 yard arrangements for CSR           forwarded to HQs for sanction.   SIP-30.11.2022
                 increase of Road No.5.     30.01.22  •  ESP approved at divisional level   SWRD-21.12.2022
                                                     and sent to Hqs on 06.09.2022.     SWR-26.12.2022
                 (Estimated cost – 0.52 crs)         •  Revised ESP approved on
                                                        16.11.2022.