Proposal Bank
               I.  Works Proposals Under PWP 2023-24 (Uploaded in IRPSM)
            Sl.   Work                      TDC      Current status                   Next step/Steps with
            No.                                                                       intermediate TDC
             a.   New Crossing Station:            •  Work proposal uploaded in IRPSM •  HQs approval awaited.
                 Proposal for new crossing            on 22.04.2022 and forwarded to  •  Letter addressed on 01.08.22
                 station (Fakhrabad Halt)             HQs for sanction.               by DRM to CE/C/Planning &
                 between NVT-BSX at KM                                                Survey for shifting of 1 new
                 438.52 with a Main Line           •  ESP approved at Division and sent  crossing station between
                 and Two Loop Lines.        31.03.24   to HQs on 13.10.2022.          UKD-VDI to FKB halt and
                                                   •  Returned from Dy. CE/ P&D on    same advised to include in
                 (Estimated cost - 19.73 crs)
                                                      16.11.2022.                     DPR of Doubling project.
                                                                                    •   Pending with Sr. DEN/ Co-
                                                                                      ord.
             b.   Timmapur:                        •  Work proposal uploaded in IRPSM  •  As advised by CTPM, Revised
                 An additional loop line for        on 22.04.2022 and forwarded to    Estimates prepared and
                 exclusive dealing of CMCT          HQs for sanction.                 uploaded in IRPSM with cost
                 bound freight trains.             •  ESP approved at divisional level   Rs. 2.99 Crs under Umbrella
                                                    and sent to Hqs on 15.07.2022.    work and submitted to
                 (Estimated cost – 2.99 crs)   --                                     CE/P&D by DRM/HYB on
                                                                                      23.06.2022.

                                                                                       •  Pending with Dy. CE/ P&D
                                                                                        since 01.12.2022.
             c.   Navipet:                         •  Work proposal uploaded in IRPSM •  HQs approval awaited.
                 Provision of additional loop        on 22.04.2022 and forwarded to  •  Due to paucity of funds under
                 line.                               HQs for sanction.                Umbrella works of PH-1600,
                                               --   •  ESP approved at divisional level   works kept under pending.
                 (Estimated cost - 8.08 crs)         and sent to Hqs on 29.06.2022.   •  ESP Pending with CSTE/PLG
                                                                                      since 24.11.2022.
             d.   Bolsa:                           •  Work proposal uploaded in IRPSM •  HQs approval awaited.
                 Provision of additional loop         on 22.04.2022 and forwarded to
                 line.                                HQs for sanction.               •  Revised ESP with
                                                   •  ESP approved at Divisional        compliance to the remarks
                 (Estimated cost – 7.53 crs)   31.03.24   approval and sent to HQs.     to be submitted by Engg.
                                                   •  Returned from HQs on              Branch.
                                                      26.10.2022.
                                                   •  Pending with Sr..DEN/Co/HYB
                                                      since 31.10.2022.
             e.   Falaknuma (PH-II):               •  Works uploaded in IRPSM and sent  •  ESP Pending with
                 Proposals for making Road          to RB on 01.12.2022 shortlisting.   CSTE/Proj. since
                 Nos. 5 & 6 as full-length   31.03.24  •  ESP approved at divisional level   30.11.2022.
                 dead end spurs.                       on 28.10.2022 and submitted to
                  (Estimated cost – 7.15 crs)          Hqs for approval.
             f.   New Crossing Station:           •  Works uploaded in IRPSM and sent   •  Advised concerned
                 Proposal for new crossing          to HQs on 21.11.2022 for forwarding   branches to arrange field
                 station (Shelgoan Halt)            to Rly Board.                       level supervisors of
                 between UMRI-SVN at KM           •  Work proposal to be uploaded in    concerned branches for
                 383.53 with One Main Line   31.03.24  IRPSM.                           conducting a Joint
                 and Two Loop Lines.              •  Abstract cost of S&T received, Engg.   Feasibility Study in order to
                                                    Abstract cost to be obtained.       prepare feasibility report,
                                                     •  ESP not prepared.               necessary sketch and
                                                                                        estimations.