I. Works Proposals Under PWP 2023-24 (Uploaded in IRPSM)
Sl. Work TDC Current status Next step/Steps with
No. intermediate TDC
a. New Crossing Station: • Work proposal uploaded in IRPSM • HQs approval awaited.
Proposal for new crossing on 22.04.2022 and forwarded to • Letter addressed on 01.08.22
station (Fakhrabad Halt) HQs for sanction. by DRM to CE/C/Planning &
between NVT-BSX at KM Survey for shifting of 1 new
438.52 with a Main Line • ESP approved at Division and sent crossing station between
and Two Loop Lines. 31.03.24 to HQs on 13.10.2022. UKD-VDI to FKB halt and
• Returned from Dy. CE/ P&D on same advised to include in
(Estimated cost - 19.73 crs)
16.11.2022. DPR of Doubling project.
• Pending with Sr. DEN/ Co-
ord.
b. Timmapur: • Work proposal uploaded in IRPSM • As advised by CTPM, Revised
An additional loop line for on 22.04.2022 and forwarded to Estimates prepared and
exclusive dealing of CMCT HQs for sanction. uploaded in IRPSM with cost
bound freight trains. • ESP approved at divisional level Rs. 2.99 Crs under Umbrella
and sent to Hqs on 15.07.2022. work and submitted to
(Estimated cost – 2.99 crs) -- CE/P&D by DRM/HYB on
23.06.2022.
• Pending with Dy. CE/ P&D
since 01.12.2022.
c. Navipet: • Work proposal uploaded in IRPSM • HQs approval awaited.
Provision of additional loop on 22.04.2022 and forwarded to • Due to paucity of funds under
line. HQs for sanction. Umbrella works of PH-1600,
-- • ESP approved at divisional level works kept under pending.
(Estimated cost - 8.08 crs) and sent to Hqs on 29.06.2022. • ESP Pending with CSTE/PLG
since 24.11.2022.
d. Bolsa: • Work proposal uploaded in IRPSM • HQs approval awaited.
Provision of additional loop on 22.04.2022 and forwarded to
line. HQs for sanction. • Revised ESP with
• ESP approved at Divisional compliance to the remarks
(Estimated cost – 7.53 crs) 31.03.24 approval and sent to HQs. to be submitted by Engg.
• Returned from HQs on Branch.
26.10.2022.
• Pending with Sr..DEN/Co/HYB
since 31.10.2022.
e. Falaknuma (PH-II): • Works uploaded in IRPSM and sent • ESP Pending with
Proposals for making Road to RB on 01.12.2022 shortlisting. CSTE/Proj. since
Nos. 5 & 6 as full-length 31.03.24 • ESP approved at divisional level 30.11.2022.
dead end spurs. on 28.10.2022 and submitted to
(Estimated cost – 7.15 crs) Hqs for approval.
f. New Crossing Station: • Works uploaded in IRPSM and sent • Advised concerned
Proposal for new crossing to HQs on 21.11.2022 for forwarding branches to arrange field
station (Shelgoan Halt) to Rly Board. level supervisors of
between UMRI-SVN at KM • Work proposal to be uploaded in concerned branches for
383.53 with One Main Line 31.03.24 IRPSM. conducting a Joint
and Two Loop Lines. • Abstract cost of S&T received, Engg. Feasibility Study in order to
Abstract cost to be obtained. prepare feasibility report,
• ESP not prepared. necessary sketch and
estimations.