                 14. Progress of Works:
                         Augmentation of Alco
                         Augmentation  of Diesel loco shed, Moula-ali  for holding capacity of 100
                           WDM2 Locos
                           Pink Book No.  594 of 2021-22, PH 4200

                    Original       Detailed
                   sanction       Estimated                          Present status
                  cost in Rs.        Cost
                   18 Crores        31.91        98% of works Completed.
                                    Crores       Solar  water  heater  installation  completed  and
                                                  commissioning works to be done
                                                 Balance  electrical  works  with  Electrical  supply  to  be
                                                  given    for   Loco     washing     shed     for   further
                                                  commissioning of the shed.


                         Augmentation of DEMU Facilities:

                           Augmentation  of  MEMU/DEMU  Car  shed  for  holding  16  MEMU/DEMU  rakes
                           with provision of 180m pit line with catwalks, stabling line of 450 m length and
                           shunting  neck  of  255  m), Admin building and OHE car shed and approaching
                           service Roads

                           Pink Book No.  624 of 2021-22, PH 4200

            Original       Detailed
            sanction      Estimated                                Present status.
          cost in Rs.        Cost
          9.61 Crores       12.83        Civil works:
                            Crores        Construction  of  OHE/TRD/SC  material  shed,  shed  approaching
                                          road with RPF post has been completed.
                                          Construction  of  Admin  Building and construction of pit line under
                                          Progress
                                           Stabling line and Shunting  line work to be started.
                                         Electrical works:
                                          Work under progress.
                                         Mechanical works (M&P items
                                          Welding plants Qty:2  Nos PO to be released
                                          Air Compressors s Qty:03  Nos
                                          Office Equipment (To be Processed)
                                         S&T.
                                          Shifting  of  the  world  S&T  exchange  to  the  existing  admin
                                          building  is  completed  and  other  works  i.e.  PA  system  and  LAN
                                          works to be started in Admin building.