Page 6 - Deep Basements Project Examples
P. 6

Godalming             London               Exeter
          01483 310600          020 3096 7567        01392 439905
          Harrogate             Bristol              Dublin
          01423 276000          0117 373 6140        (01) 554 6210





      Deep Basements - Example Projects





      Subsea 7 Office HQ, Sutton, Surrey                       Services
      Robust Monitoring Approach Keeps Network Rail              Ÿ Site investigation
      on Track
                                                                 Ÿ Temporary Works Design
      The project was for construction of a high-tech HQ office in
                                                                 Ÿ Numerical and Ground Modelling
      Sutton for offshore engineers Subsea 7. The £40m new
      building has five storeys above ground plus a 20,000m³,    Ÿ Observational Methods Approach
      5m deep basement including a car park.                     Ÿ Monitoring of Network Rail Asset


      Construction of the new building car park ramp had the   The catalyst for these design changes was CGL's
      potential to undermine the neighbouring Network Rail     supplementary site investigation around the basement
      South West (NRSW) line. Other critical constraints for the   perimeter and CGL's focus on understanding realistic
      basement included the need for temporary retaining       geotechnical design parameters, hydrology and predicted
      works to provide working space and to protect sensitive   ground movement modelling in structured chalk.
      fuel storage tanks, existing trees, neighbouring buildings,
      highways and sewers.                                     The main achievement of the project was delivery of a
                                                               substantial basement alongside the railway that involved
      CGL partnered with Galliford Try (GT) as geotechnical    only minimal temporary works on three sides with none at
      Temporary Works Engineer and CGL also advised GT on      the NR boundary, which benefitted from observational
      ground movements.                                        methods backed by robust monitoring.


      Liaison with NRSW was undertaken by CGL which            CGL used ground modelling software including WALLAP,
      identified the need for specifically targeted supplementary   GWALL, FLAC Slope and PDISP to justify the proposed
      site investigation, slope stability analysis, temporary works   scheme and efficiencies in both temporary and permanent
      design and exemplary multi-hierarchy protocols for       works.
      monitoring and trigger level action and contingency
      planning.                                                The robust monitoring scheme paid dividends in providing
                                                               reliable data to justify efficiencies in design. An example of
      Following successes using Observational Methods in chalk   this was the back analysis of King Post deflections to justify
      for previous projects, a pragmatic approach was adopted   early prop removal ahead of constructing the ground floor
      for a cost saving combination of open cut excavation and   slab.
      King Posts with robust monitoring controls, as opposed to
      a contiguous pile wall solution.






















                                           visit our website at cgl-uk.com
   1   2   3   4   5   6   7   8