ELECTRICAL SYSTEMS


                                                SUMMARY OF CONTROL MEASURES:-



                                                ●      heck for existing services and check layout
                                                       drawings;


                                                ●      Provide barriers and  safety warning signage
                                                       to task work area & open electrical panels;


                                                ●      Before back into use, replace guards and
                                                       prevent access to live electrical panels;


                                                ●      Test the circuit to ensure all electrical
                                                       connections are safe;


                                                ●      Replace all guards, close electrical panels,
                                                       remove barriers and safety signage;


                                                ●      Sign off electrical Test Certificate and issue

                                                       to the client;

                                                ●      Close out Permit-to-Work and communicate

                                                       the work equipment is safe to use.