3.3.6  Wildlife Impact Study Report                Management Plan if required, which then be
                Preparation                                        submitted to DOE for EIA Report submission
                                                                   and approval. To  ensure a quality Wildlife
                       The Wildlife Impact Study team leader       Impact Study Report before submission for
                will  coordinate the  writing of the Wildlife      approval, consultants can refer Report Quality
                Impact Study Report and review it thoroughly       Control      Assessment       (see     3.3.7).
                to ensure it encompasses all the elements in
                the TOR and is comprehensive, coherent,            3.3.9  Compliance Monitoring
                balanced,     impartial    and     technically
                acceptable for submission to the authorities.             If the proposed project is approved for
                The Wildlife Impact Study consultant acting        implementation, the project will proceed to
                as the team leader shall extract and               the    subsequent     phases     of   design,
                summarise the major findings of the reports        construction,  and  operation.  Compliance

                and place them in the appropriate chapters in      monitoring activities will be conducted by
                the Wildlife Impact Study Report.                  PERHILITAN, to ensure compliance with the
                                                                   requirements set out in this Guidance
                3.3.7  Wildlife Impact Study Report                Document will fulfil the Project Proponent’s
                Review                                             obligation to Wildlife Conservation Act

                                                                   (WCA) 2010 (Act 716). Monitoring process is
                       The Wildlife Impact Study Report must
                                                                   important to ensure that the Wildlife Impact
                be submitted to the Director General of
                                                                   Study covered all TOR-wildlife component,
                PERHILITAN within the stipulated periods for       complies  with the  standard  field  methods,
                approval. The  Wildlife Impact Study Report
                                                                   study design and analysis, wildlife being
                Review for projects under the First and            immediately released after identification, and
                Second Schedule will be conducted at the
                                                                   removal of traps after Wildlife Impact Study
                State    PERHILITAN      and     PERHILITAN
                                                                   being conducted. This process will also assess
                Headquarters,    respectively.  As    general      the implementation of mitigation measures
                guidance,   the   Project   Proponent     and
                                                                   proposed in Wildlife Impact Study Report by
                consultants can refer to the Wildlife Impact       Project Proponent. Site inspection will also be
                Study Report Quality Self-Assessment Tool
                                                                   conducted if necessary. This monitoring
                for Wildlife Impact Study Report (Appendix).
                                                                   process will serve the purpose of ensuring the
                This is to ensure a quality Wildlife Impact        Wildlife Impact Study conditions of approval,
                Study Report is prepared before submission
                                                                   particularly proposed mitigation measures,
                for approval by PERHILITAN.                        are complied with. In this phase, PERHILITAN
                                                                   will assess the overall project compliance and
                3.3.8  Decision Making
                                                                   opportunity for optimisation  and further
                                                                   improvement in wildlife management of the
                       A decision is made at the end of the
                                                                   project,   also   known     as    Compliance
                review process to approve or reject the
                                                                   Monitoring.
                Wildlife Impact Study Report. Letter of
                confirmation will be issued after Review
                Meeting,    with   statement     of   Wildlife








         14  GUIDANCE DOCUMENT ON  WILDLIFE
             IMPACT STUDY FOR IN ENVIRONMENTAL
             IMPACT ASSESSMENT (EIA)