            Dear Andrew,

            RE: SAG MILL BUILDING VIRTUAL INSPECTION ASSESSMENT

            [Our Reference: AMLKCa-LET-102 REV 0]

            As  requested,  Yenem  Engineering  Services  Pty Ltd (Yenem)  has  completed the  structural  remediation
            design for the sag mill building at Peak Gold Mine to ensure structural integrity. Peak Gold Mine Pty Ltd
            (PGM) requested Yenem to attend site for an initial structural inspection to review the current structural
            condition to ensure the current status is in line with any assumptions made during the design phase.

            Due to the current COVID-19 border restriction, our engineers could not attend site inspection in person. A
            remote visual inspection was arranged for this task as an alternative. Yenem’s drone pilot, Brad Guest,
                                        th
                                                th
            attended the site between 24  and 26  August 2020 to collect enough information for the creation of a
            360  Pano  model.  A  Yenem  engineer,  Shawn  Cao,  can  then  review the model for  a  virtual structural
            inspection to provide comments and recommendations accordingly.