5. The SHS temporary column can be removed after the completion of all the repair works. The
UC column is recommended to keep in place unless it blocks the walkway.
This is to confirm that the sag mill building has been inspected and the remedial works can be carried with
the proposed remedial methodology with above-mentioned recommendations. All locations can be
referred to the removing sequence and repair methodology documents. The 360 pano inspection model
will be issued together with this letter for reference.
Please do not hesitate to contact the undersigned should you have any queries or further requirements.
Sincerely,
Yenem Engineering Services
John Zhang
Principal Structural Engineer
B.E (Civil), MEng (Structural) MIEAust
Page 4