5.    The SHS temporary column can be removed after the completion of all the repair works. The
                        UC column is recommended to keep in place unless it blocks the walkway.






















            This is to confirm that the sag mill building has been inspected and the remedial works can be carried with
            the proposed  remedial methodology  with above-mentioned recommendations.  All locations can be
            referred to the removing sequence and repair methodology documents. The 360 pano inspection model
            will be issued together with this letter for reference.

            Please do not hesitate to contact the undersigned should you have any queries or further requirements.

            Sincerely,


            Yenem Engineering Services



            John Zhang
            Principal Structural Engineer


            B.E (Civil), MEng (Structural) MIEAust